Aubrey, TX 76227 · City Of Aubrey
Aubrey street project adds sidewalks, ramps and crosswalks
Aubrey’s 2024 Street Rehabilitation Project includes concrete sidewalks, barrier-free ramps and crosswalks at locations including Countryside Drive and Winn Ridge Boulevard. The project was registered with TDLR on October 11, 2024, and the applicant estimated its cost at $54,364.
Summarized from Texas Department of Licensing and Regulation records · updated Oct 11, 2024
- Projects
- 1
- 1 filings
- Latest filing
- Oct 11, 2024
- since Oct 11, 2024
- Largest scope
- 3,500 sf
- Estimated cost
- $54K
- state registration
Where this project stands
Completed2024 Street Rehabilitation Project
3,500 sq ft · $54K est.
- RegisteredOct 11, 2024
- Plan review
- ConstructionJun '24 – Nov '24
- Inspected
- Closed
Ran as a 6-month build.
4 contacts on this project · 3 phone numbers
Permit & project history
1 project387 square yards of 4-inch thick, 5-foot wide reinforced concrete sidewalk, 2 no. of barrier free ramps, 820 linear feet of crosswalk. — creek estates lift station, aubrey area library, countryside dr, michelle st. winn ridge blvd, etc
TDLR project registrationRenovation/AlterationProject Closed3,500 sq ft$54K est.- Project #
- TABS2025003042
- Tenant / owner
- 2024 Street Rehabilitation Project
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 226 Countryside Dr, Aubrey, TX 76227 698 Coleman St, Aubrey, TX 76227
What is being built in Aubrey’s 2024 Street Rehabilitation Project?
The project includes 387 square yards of reinforced concrete sidewalk, two barrier-free ramps and 820 linear feet of crosswalk. TDLR registration TABS2025003042 lists the work as a renovation or alteration.
Where is the Aubrey street rehabilitation work taking place?
The project description lists locations including Countryside Drive, Michelle Street and Winn Ridge Boulevard, as well as the Creek Estates lift station and Aubrey Area Library. It does not specify the exact work at each location.
When was the Aubrey street project registered?
The project was registered with the Texas Department of Licensing and Regulation on October 11, 2024.
How much will the 2024 Street Rehabilitation Project cost?
The applicant’s estimated cost for the project is $54,364, according to TDLR registration TABS2025003042.
Is the Aubrey street rehabilitation project still underway?
The TDLR record lists the project status as closed.