1400 N IH 35 Svrd Sb

Austin, TX 78701 · Central Health

Clinical education center renovation for short-term residential stays

Austin permits indicate a phased renovation of the existing clinical education center at 1400 N IH 35 Svrd Sb into residential congregate living for stays of up to 50 days. Building permits for phases 1 and 2 were filed May 5, 2025, with related electrical, mechanical and plumbing permits filed through June 2. Plans list shared dining without a kitchen and staff offices.

Summarized from City of Austin, Texas Department of Licensing and Regulation records · updated Jun 2, 2025

Projects
11
11 filings
Latest filing
Jun 2, 2025
since Feb 4, 2025
Largest scope
33,000 sf
Estimated cost
$2.4M
state registration

Where this project stands

Finaled

Phase 1 -renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

  1. AppliedFeb 21, 2025
  2. IssuedJun 2, 2025
  3. WorkJun '25 – Jul '25
  4. Final inspectionJul 15, 2025

Passed final inspection Jul 15, 2025.

1 contact on this project · 1 phone number

Permit & project history

11 projects
  1. Phase 1 -renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    Phase 1 -renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    City of Austin permitPlumbing PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  2. Phase 2-renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days. auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    Phase 2-renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days. auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    City of Austin permitPlumbing PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  3. Phase 3- renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days. auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    Phase 3- renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days. auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    City of Austin permitPlumbing PermitWithdrawn
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  4. Phase 2-renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days. auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    Phase 2-renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days. auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    City of Austin permitMechanical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  5. Phase 1 -renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    Phase 1 -renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    City of Austin permitMechanical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  6. Phase 1 -renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    Phase 1 -renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  7. Phase 2-renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days. auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    Phase 2-renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days. auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  8. Phase 1 -renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    Phase 1 -renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    City of Austin permitBuilding PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  9. Phase 3- renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days. auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    Phase 3- renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days. auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    City of Austin permitBuilding PermitWithdrawn
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  10. Phase 2-renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days. auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    Phase 2-renovation of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days. auxiliary spaces include shared dining without kitchen and staff offices. this project will be phased

    City of Austin permitBuilding PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  11. Interior renovation of approx. 33,000 s.f. of existing clinical education center into a residential congregate living for occupants to stay not longer than 50 days. auxiliary spaces include shared dining without kitchen and staff offices. — cec

    TDLR project registrationRenovation/AlterationProject Closed33,000 sq ft$2.4M est.
    Tenant / owner
    Central Health Respite Center
    Design firm
    Pro
    Contact
    Pro

Sources: City of Austin · Texas Department of Licensing and Regulation

Questions about 1400 N IH 35 Svrd Sb

What is being built at 1400 N IH 35 Svrd Sb?

Permits describe a phased renovation of an existing clinical education center into residential congregate living for stays of up to 50 days. Plans include shared dining without a kitchen and staff offices.

Is 1400 N IH 35 Svrd Sb being converted into housing?

City of Austin permits describe residential congregate living, with occupants staying no longer than 50 days. The records do not identify a tenant or operator.

When were permits filed for the renovation at 1400 N IH 35 Svrd Sb?

Phase 1 and 2 building permits were filed May 5, 2025. Related permits were filed from May 6 through June 2, 2025.

What do the permits say about dining at 1400 N IH 35 Svrd Sb?

The permit descriptions list shared dining without a kitchen, along with staff offices, as auxiliary spaces for the project.

Were all phases of the 1400 N IH 35 Svrd Sb project approved?

The phase 1 and phase 2 building permits are marked Final. The phase 3 building permit, 2025-052260 BP, and plumbing permit, 2025-052260 PP, are marked Withdrawn.