Generator and transfer switch work at existing Austin fire station

Permits indicate work to replace a generator and automatic transfer switch at the existing fire station at 3009 Windsor Rd, and add a docking station on a new concrete equipment pad. The building permit was filed July 30, 2024, followed by an electrical permit on October 18, 2024, and a plumbing permit on January 30, 2025. All three permits are listed as final.

Summarized from City of Austin records · updated Jan 30, 2025

Projects
3
3 filings
Latest filing
Jan 30, 2025
since Jul 30, 2024
Largest scope
—
Listed value
—

Where this project stands

Finaled

Replace an existing option generator and automatic transfer switch and add a docking station on the new concrete equipment pad for the existing fire station. site plan exemption not require less than 100 sq ft

  1. AppliedJul 22, 2024
  2. IssuedJan 30, 2025
  3. WorkJan '25 – Feb '25
  4. Final inspectionFeb 6, 2025

Passed final inspection Feb 6, 2025.

1 contact on this project · 1 phone number

Permit & project history

3 projects
  1. Replace an existing option generator and automatic transfer switch and add a docking station on the new concrete equipment pad for the existing fire station. site plan exemption not require less than 100 sq ft

    Replace an existing option generator and automatic transfer switch and add a docking station on the new concrete equipment pad for the existing fire station. site plan exemption not require less than 100 sq ft

    City of Austin permitPlumbing PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  2. Replace an existing option generator and automatic transfer switch and add a docking station on the new concrete equipment pad for the existing fire station. site plan exemption not require less than 100 sq ft

    Replace an existing option generator and automatic transfer switch and add a docking station on the new concrete equipment pad for the existing fire station. site plan exemption not require less than 100 sq ft

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  3. Replace an existing option generator and automatic transfer switch and add a docking station on the new concrete equipment pad for the existing fire station. site plan exemption not require less than 100 sq ft

    Replace an existing option generator and automatic transfer switch and add a docking station on the new concrete equipment pad for the existing fire station. site plan exemption not require less than 100 sq ft

    City of Austin permitBuilding PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro

Sources: City of Austin

Questions about 3009 Windsor Rd

What work is permitted at 3009 Windsor Rd in Austin?

Permits describe replacing the existing generator and automatic transfer switch and adding a docking station on a new concrete equipment pad for the existing fire station.

Is a new fire station being built at 3009 Windsor Rd?

The permits describe equipment work for an existing fire station, not construction of a new fire station.

When was work at 3009 Windsor Rd permitted?

The building permit was filed July 30, 2024; the electrical permit followed on October 18, 2024, and the plumbing permit on January 30, 2025.

What are the permit numbers for 3009 Windsor Rd?

The records list permits 2024-095468 BP, 2024-095468 EP and 2024-095468 PP.

Are the permits for 3009 Windsor Rd final?

Yes. The City of Austin records list all three permits—building, electrical and plumbing—as final.

Is a new equipment pad part of the work at 3009 Windsor Rd?

Yes. The permit description says the docking station will be installed on a new concrete equipment pad and notes that a site plan exemption is not required for work under 100 square feet.

Also being built nearby