7005 Creighton Ln: 3 projects on record
City of Austin lists 3 filings across 3 projects at 7005 Creighton Ln, Austin, TX 78723 since April 18, 2024. The most recent, filed November 8, 2024, covers: “Installation of a 100a automatic transfer switch/load center relocation of (2) branch circuits (sub-panel and a/c) from exterior main panel to new ats/load center and installation of an 18kw whole home generator”.
Compiled from City of Austin records · updated Nov 8, 2024
- Projects
- 3
- 3 filings
- Latest filing
- Nov 8, 2024
- since Apr 18, 2024
- Largest scope
- —
- Listed value
- —
Where this project stands
FinaledInstallation of a 100a automatic transfer switch/load center relocation of (2) branch circuits (sub-panel and a/c) from exterior main panel to new ats/load center and installation of an 18kw whole home generator
- AppliedOct 28, 2024
- IssuedNov 8, 2024
- WorkNov '24 – Nov '24
- Final inspectionNov 12, 2024
Passed final inspection Nov 12, 2024.
1 contact on this project · 1 phone number
Permit & project history
3 projectsInstallation of a 100a automatic transfer switch/load center relocation of (2) branch circuits (sub-panel and a/c) from exterior main panel to new ats/load center and installation of an 18kw whole home generator
Installation of a 100a automatic transfer switch/load center relocation of (2) branch circuits (sub-panel and a/c) from exterior main panel to new ats/load center and installation of an 18kw whole home generator
City of Austin permitElectrical PermitFinal- Record
- 2024-144163 EP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Install a gas line for a generator
Install a gas line for a generator
City of Austin permitPlumbing PermitFinal- Record
- 2024-114546 PP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
***storm damage*** replace existing elect due to storm damage
***storm damage*** replace existing elect due to storm damage
City of Austin permitElectrical PermitFinal- Record
- 2024-045065 EP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 7005 Creighton Ln
What is being built at 7005 Creighton Ln?
The latest filing (City of Austin permit 2024-144163 EP, November 8, 2024) covers installation of a 100a automatic transfer switch/load center relocation of (2) branch circuits (sub-panel and a/c) from exterior main panel to new ats/load center and installation of an 18kw whole home generator.
How many permits and filings does 7005 Creighton Ln have?
3 filings across 3 projects, from April 18, 2024 to November 8, 2024.
Is there other construction near 7005 Creighton Ln?
Yes. Nearby filings include 7007 Creighton Ln (rebuild and upgrade main service to home. install grounding system to include cold water bond and intersystem bond, Nov 18, 2026); 7009 Creighton Ln (new install, May 27, 2025); 2502 Colby Cv (express: foundation repair revision 1: add plumbing permit, Nov 13, 2025).
How do I get alerts for new permits at 7005 Creighton Ln?
Watch this address on groundranger and you'll get an email when a new permit or project filing appears here or nearby.
Also being built nearby
All of 78723- 7007 Creighton LnNov 18, 2026Rebuild and upgrade main service to home. install grounding system to include cold water bond and intersystem bond · 25 m away
- 7009 Creighton LnMay 27, 2025New install · 47 m away
- 2502 Colby CvNov 13, 2025Express: foundation repair revision 1: add plumbing permit · 59 m away
- 7010 Creighton LnApr 23, 2026Scope of work: remove cast iron pipes running to all drains replace with new pvc. this will include installation of new drain lines and tunnels. (4) tunnel access points for drain lines. excavate to remove soil and pour gravel. additionally we will change the yard line from the house to the street and install clean outs required · 78 m away
- 7013 Creighton LnNov 24, 2025Tunnel under slab up to 38 to expose and replace cast iron building drain. tunnel access will on side of home. we will also be performing two spot repairs in yard on building sewer · 92 m away
- 7208 Marywood CirDec 15, 2023Remodel existing bedroom and kitchen adding new bath and utility room. window replacements/modifications throughout. interior renovation per plan. modify rear porch extents. remove fireplace and chimney · 104 m away
- 6905 Creighton LnNov 11, 2026Excavate 39 tunnel to repair main drain line under house · 110 m away
- 7215 Marywood CirDec 8, 2023Tee into external gas line and run additional line for generator installation · 111 m away
- 2503 Colby CvSep 20, 2025Repair kitchen sink and washing machine waste lines by tunneling under slab from outside house · 117 m away
- 7205 Marywood CirMar 14, 2025Express: replace windows like for like · 125 m away
- 2404 Akron CvFeb 13, 2024Tunnel - replace all pvc underground · 126 m away
- 7016 Creighton LnFeb 27, 2025Remodel and fence change layout of kitchen and master create new main drain add privacy fence project to include the following scope: replacement of complete existing central heat and air system relocation of ductwork new hood vent and new exhaust vents (roll in 2024-051655 mp) · 146 m away