Electrical service rebuild permitted at 5701 Trailridge Dr
A City of Austin permit covers a service-only electrical rebuild for a 200-amp service at 5701 Trailridge Dr. The permit was filed on April 21, 2026, and is listed as final.
Summarized from City of Austin records · updated Apr 21, 2026
- Projects
- 1
- 1 filings
- Latest filing
- Apr 21, 2026
- since Apr 21, 2026
- Largest scope
- —
- Listed value
- —
Where this project stands
FinaledService only rebuild. 200a
- AppliedApr 2, 2026
- IssuedApr 21, 2026
- WorkApr '26 – May '26
- Final inspectionMay 6, 2026
Passed final inspection May 6, 2026.
1 contact on this project · 1 phone number
Permit & project history
1 projectService only rebuild. 200a
Service only rebuild. 200a
City of Austin permitElectrical PermitFinal- Record
- 2026-039725 EP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 5701 Trailridge Dr
What is being built at 5701 Trailridge Dr?
The City of Austin permit describes a service-only electrical rebuild for a 200-amp service. It does not describe a new building.
When was the electrical permit filed?
The permit was filed on April 21, 2026. Its number is 2026-039725 EP.
Is the permit for a new home at 5701 Trailridge Dr?
The available permit record describes an electrical service rebuild, not new home construction.
What is the status of permit 2026-039725 EP?
The City of Austin lists the electrical permit as final.
What does a service-only rebuild mean at this address?
The permit description says “Service only rebuild. 200a,” indicating work on the electrical service. The record does not provide further details.
What is being permitted near McCarty Triangle LLP?
At 5701 Trailridge Dr, about 137 meters from McCarty Triangle LLP at 3407 Northland Drive, a service-only electrical rebuild was permitted on April 21, 2026.
Also being built nearby
All of 78731- 5705 Highland Hills DrDec 5, 2023Replace old wiring in attic. add a subpanel and new circuits. add various lights plugs and back porch wiring · 50 m away
- 5700 Trailridge DrDec 2, 202555 tunnel below the foundation to replace entire drain system. 2 access holes - front right · 52 m away
- 5750 Balcones DrOct 30, 2024Replacement of complete existing central heat and air system with or without duct work · 64 m away
- 5702 Trailridge DrApr 9, 2025Replace sewer line · 68 m away
- 5707 Trailridge DrJul 11, 2025Excavate 60 trench to repair main drain in yard · 81 m away
- 5704 Trailridge DrOct 8, 2026Replacing the homes under-slab drain lines installing a new pex water distribution system and replacing the sewer line from the home to the city connection · 82 m away
- 5701 Highland Hills DrNov 16, 2026Construct new driveway approach of 8 ft. no sidewalk inspection per plan review · 97 m away
- 5706 Trailridge DrMar 18, 2024Interior remodel of existing sfr · 102 m away
- 5711 Trailridge DrJun 27, 2025Re pipe sewer system under home and also the sewer line to the street. a tunnel of approximately 40 feet from the corner of the home to the city cleanout will be excavated. another 90 foot tunnel will be excavated under the slab to access underneath the home · 135 m away
- 3407 Northland Drive · Mccarty Triangle LlpJul 15, 2024Griffi — renovation/alteration — interior renovation · 137 m away
- 5770 N Mopac Expy Svrd SbMay 29, 2025Channel letters on raceways · 158 m away
- 5770 Mopac Expy SvrdMar 2, 2007Zuzu's restaurant · 158 m away