A one-story data center building with five colos and about 244,676 square feet is planned at 18844 FM 1957 in Castroville. Its TDLR project registration was filed July 25, 2024; the applicant estimated the project cost at $482.6 million.

Summarized from Texas Department of Licensing and Regulation records · updated Jul 25, 2024

Projects
1
1 filings
Latest filing
Jul 25, 2024
since Jul 25, 2024
Largest scope
244,676 sf
Estimated cost
$483M
state registration

Where this project stands

Under construction

SAT82 Data Center

244,676 sq ft · $483M est.

  1. RegisteredJul 25, 2024
  2. Plan review
  3. ConstructionApr '26 – Feb '28
  4. Inspected
  5. Closed
33% through of a 22-month buildApr 11, 2026 → Feb 8, 2028

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. SAT82 Data Center

    Construction of one story building with 5 colos for a data center. approximate 244,676 square foot of gross building area — sat82 data center

    TDLR project registrationNew ConstructionReview Complete244,676 sq ft$483M est.
    Tenant / owner
    Sat82 Data Center
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 18844 FM 1957 Castroville

What is being built at 18844 FM 1957 in Castroville?

A TDLR registration describes the SAT82 Data Center, a planned one-story building with five colos and about 244,676 square feet. The registration was filed July 25, 2024, under project number TABS2024023976.

How big is the SAT82 Data Center?

The TDLR registration lists approximately 244,676 square feet of gross building area.

When was the Castroville data center project filed?

The SAT82 Data Center registration was filed with TDLR on July 25, 2024. Its project number is TABS2024023976.

How much will the SAT82 Data Center cost?

The applicant estimated the project cost at $482.6 million in the TDLR registration. This is an estimate, not a confirmed final cost.

Is the SAT82 Data Center a new construction project?

Yes. The TDLR registration identifies the project type as new construction and describes a one-story data center building.