3241 Hwy 90 Alternate Tx, Columbus, TX 77442
Columbus, TX 77442 · Rock Island Generation Plant
Rock Island Generation Plant power house planned in Columbus
A new approximately 27,200-square-foot electrical power house facility is planned for the Rock Island Generation Plant at 3241 Hwy 90 Alternate Tx in Columbus. The project was registered with TDLR on June 8, 2026; the registration lists an applicant-estimated project cost of $175 million.
Summarized from Texas Department of Licensing and Regulation records · updated Jun 8, 2026
- Projects
- 1
- 1 filings
- Latest filing
- Jun 8, 2026
- since Jun 8, 2026
- Largest scope
- 27,200 sf
- Estimated cost
- $175M
- state registration
Where this project stands
Under constructionROCK ISLAND GENERATION PLANT
27,200 sq ft · $175M est.
- RegisteredJun 8, 2026
- Plan review
- ConstructionJun '26 – Jun '27
- Inspected
- Closed
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectNew construction, approximately 27,200 sq ft, fire sprinkled, electrical power house facility with restroom, breakroom and control room. — rock island generation plant
TDLR project registrationNew ConstructionReview Complete27,200 sq ft$175M est.- Project #
- TABS2026022339
- Tenant / owner
- Rock Island Generation Plant
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 3241 Hwy 90 Alternate Tx, Columbus, TX 77442
What is being built at 3241 Hwy 90 Alternate Tx in Columbus?
A new electrical power house facility is planned at the Rock Island Generation Plant. The approximately 27,200-square-foot building is described as including a restroom, breakroom and control room.
When was the Rock Island Generation Plant project registered?
The project was registered with the Texas Department of Licensing and Regulation on June 8, 2026. Its registration number is TABS2026022339.
How large is the planned power house in Columbus?
The TDLR registration describes the new facility as approximately 27,200 square feet.
How much will the Rock Island Generation Plant project cost?
The TDLR registration lists an applicant-estimated project cost of $175 million. This is an estimate for the project, not a reported final cost.
What will the new Rock Island Generation Plant building include?
The registration describes an electrical power house facility with a restroom, breakroom and control room. It also says the building will be fire sprinkled.
Has the Rock Island Generation Plant project been approved?
The TDLR registration lists the project status as “Review Complete.” The record does not provide further approval details.