groundranger
Active · latest filing Sep 2026Commercial

4650 FM 1694, Robstown, TX 78380

Corpus Christi, TX 78380 · Beacon Point Dc LLC Aka Lon Hill Infrastructure LLC

657,130-square-foot data center registered in Corpus Christi

A 657,130-square-foot data center, along with a guardhouse, fire water tank and pump, and exterior mechanical and electrical support structures, is planned at 4650 FM 1694. The project was registered with the Texas Department of Licensing and Regulation on September 9, 2026.

Summarized from Texas Department of Licensing and Regulation records · updated Sep 9, 2026

Projects
1
1 filings
Latest filing
Sep 9, 2026
since Sep 9, 2026
Largest scope
657,130 sf
Estimated cost
$399M
state registration

Where this project stands

In state plan review

Beacon Point Data Center Project

657,130 sq ft · $399M est.

  1. RegisteredSep 9, 2026
  2. Plan reviewnow
  3. ConstructionSep '26 – Nov '27
  4. Inspected
  5. Closed

Design is filed with the state. Subcontractors and suppliers are usually picked around now.

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. Type iib construction of a fully sprinklered, 657,130 square foot, mixed use occupancy (primarily b) data center building and associated guardhouse, fire water tank and pump, and exterior mechanical and electrical support structures. — beacon point data center

    TDLR project registrationNew ConstructionProject Registered657,130 sq ft$399M est.
    Tenant / owner
    Beacon Point Data Center Project
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 4650 FM 1694, Robstown, TX 78380

What is being built at 4650 FM 1694?

A 657,130-square-foot data center is planned, with a guardhouse, fire water tank and pump, and exterior mechanical and electrical support structures. The TDLR registration is TABS2027000611, dated September 9, 2026.

How large is the Beacon Point Data Center Project?

The registered project lists 657,130 square feet for the data center building.

When was the data center project registered?

The Texas Department of Licensing and Regulation registration, TABS2027000611, is dated September 9, 2026.

What will be included with the data center?

The registration describes a guardhouse, fire water tank and pump, and exterior mechanical and electrical support structures in addition to the data center building.

What is the estimated cost of the Beacon Point Data Center Project?

The TDLR registration lists an estimated project cost of $398,985,153. This is the applicant's estimate for the project.

Email me when plan review is complete