3001 Maple Ave
Dallas, TX 75201 · Bva Group, Mitsui Fudosan America + 1 more
BVA Group suite 500 finish-out and tenant improvements
Permits indicate a first-time finish-out for BVA Group in suite 500, along with work in the corridors and lobby and an expansion of existing tenant space. City of Dallas permits were filed from July 14, 2025, through November 12, 2026; recent work includes electrical, plumbing and mechanical systems.
Summarized from City of Dallas, Texas Department of Licensing and Regulation records · updated Nov 12, 2026
- Projects
- 28
- 28 filings
- Latest filing
- Nov 12, 2026
- since Feb 21, 2024
- Largest scope
- 11,283 sf
- Estimated cost
- $2.3M
- state registration
Permit & project history
28 projectsJob#26178h bva remodel. furnish and install fan coil unitsexhaust fansupply grilles lay in return grilles slot diffusers sidewall grilles
Job#26178h bva remodel. furnish and install fan coil unitsexhaust fansupply grilles lay in return grilles slot diffusers sidewall grilles
City of Dallas permitCommercial Mechanical PermitFurnish and install 11- coil units 1- exhaust fan air devices 29-supply grilles 37- lay in return grilles 34- slot diffusers 14- sidewall grilles demolition- 4- existing fan coil units
Furnish and install 11- coil units 1- exhaust fan air devices 29-supply grilles 37- lay in return grilles 34- slot diffusers 14- sidewall grilles demolition- 4- existing fan coil units
City of Dallas permitCommercial Mechanical PermitFirst time finish out for suite 500 for a tenantnamed bva group. also the first time finish out for thecorridors and lobby
First time finish out for suite 500 for a tenantnamed bva group. also the first time finish out for thecorridors and lobby
City of Dallas permitCommercial Electrical PermitFirst time finish out for suite 500 for a tenant named bva group. also the first time finish out for the corridors and lobby
First time finish out for suite 500 for a tenant named bva group. also the first time finish out for the corridors and lobby
City of Dallas permitCommercial New Construction PermitFurnish and install 5- fan coil units 20-supply grilles 7- lay in return air grilles 4- side wall grilles piping- condensate drain lines and cws/r
Furnish and install 5- fan coil units 20-supply grilles 7- lay in return air grilles 4- side wall grilles piping- condensate drain lines and cws/r
City of Dallas permitCommercial Mechanical PermitTenant improvement — maple terrace
TDLR project registrationRenovation/AlterationReview Complete11,283 sq ft$2.3M est.- Project #
- TABS2026023231
- Tenant / owner
- Bva Group
- Design firm
- Pro
- Contact
- Pro
Manufacture (eaton) is to repair internal control wiring within main switchboard ms1. also need to add gfi protection to ms2 switchgear. both switchgears will require utility shutdown and meter release from city
Manufacture (eaton) is to repair internal control wiring within main switchboard ms1. also need to add gfi protection to ms2 switchgear. both switchgears will require utility shutdown and meter release from city
City of Dallas permitCommercial Electrical Permit7 fan powered boxes, 2 vav boxes, 1 exhaust fan, air duct as shown, 11 supply grilles, 1 lay in return aire grille, 22 slot diffusers, 32 sidewall grilles
7 fan powered boxes, 2 vav boxes, 1 exhaust fan, air duct as shown, 11 supply grilles, 1 lay in return aire grille, 22 slot diffusers, 32 sidewall grilles
City of Dallas permitCommercial Mechanical PermitAlteration to existing building, tenant finish out — maple terrace
TDLR project registrationRenovation/AlterationProject Closed5,111 sq ft$750K est.- Project #
- TABS2025005114
- Tenant / owner
- Mitsui Fudosan America
- Design firm
- Pro
- Contact
- Pro
Tenant improvement to existing building suite — maple terrace
TDLR project registrationRenovation/AlterationProject Closed4,763 sq ft$625K est.- Project #
- TABS2024012084
- Tenant / owner
- Hig Capital
- Design firm
- Pro
- Contact
- Pro
White box; no build back;non-load bearing walls; co/finish out permits are req prior to occupancy
White box; no build back;non-load bearing walls; co/finish out permits are req prior to occupancy
City of Dallas permitBuilding (BU) Commercial Renovation$34
Sources: City of Dallas · Texas Department of Licensing and Regulation
Questions about 3001 Maple Ave
What is being built at 3001 Maple Ave, Dallas?
Permits describe a first-time finish-out for BVA Group in suite 500, plus improvements to the corridors and lobby and an expansion of existing tenant space. The records also include mechanical, electrical and plumbing work.
Is BVA Group moving into 3001 Maple Ave?
A Dallas permit filed August 18, 2026, describes a first-time finish-out for suite 500 for BVA Group. The records do not state a move-in date.
When were permits filed for work at 3001 Maple Ave?
The earliest filing in the records is dated July 14, 2025, and the latest is November 12, 2026. A permit for mechanical work was filed November 12, 2026.
What work is planned for suite 500 at 3001 Maple Ave?
A commercial new-construction permit filed August 18, 2026, describes a first-time finish-out for suite 500 for BVA Group. Related permits cover electrical, plumbing and mechanical work.
How much is the 3001 Maple Ave project expected to cost?
The Texas Department of Licensing and Regulation record lists an applicant-estimated project cost of $2.3 million. This is an estimate, not a confirmed final cost.
What's being built near Legacy Knight Expansion at 3001 Maple Terrace?
At 3001 Maple Ave, permits indicate a suite 500 finish-out for BVA Group, corridor and lobby work, and an expansion of existing tenant space. The records do not describe a new standalone building.
Also being built nearby
All of 75201- 3001 MapleDec 2, 2025Install plumbing per plans
- 3001 Maple Avenue · 3001 Maple LPApr 24, 2025The related companies — renovation/alteration — tenant improvement
- 3001 Maple Avenue Suites 310, 320 And 330 · 3001 Maple LPApr 24, 20253rd floor spec suites — renovation/alteration — tenant improvement
- 3001 Maple Terrace · 3001 Maple LPJun 16, 2026Legacy knight expansion — renovation/alteration — tenant improvement
- 3003 Maple AveFeb 5, 2026Manufacture (eaton) is to repair internal control wiring within main switchboard ms1. also need to add gfi protection to ms2 switchgear. both switchgears will require utility shutdown and meter release from city · 2 m away
- 3008 Maple AveJul 21, 2025Repair grease underground broken pipe · 14 m away
- 3040 Maple Ave. 2nd · Old Parkland East Campus - Providence HallDec 3, 20252nd floor corridor — additions to existing building — tenant improvement · 37 m away
- 2927 Maple Avenue · Cwi Dallas Hotel, LPMay 28, 2025The stoneleigh hotel renovation — renovation/alteration — hotel renovation to the basement and level one public spaces · 91 m away
- 2927 Maple AveApr 1, 2026Electrical work at awning near the pool area. removing, replacing and installing fixtures · 91 m away
- 2926 Maple AveApr 20, 2026Zo bc commercial addition of a 1,380 square foot outdoor patio consisting of steel sub frame overlaid with weather-treated lumber · 92 m away
- 3102 Maple AveJan 22, 2026Plumbing remodel of existing space. space was previously a full floor occupant and is now divided into multiple tenant spaces · 98 m away
- 3102 Maple Avenue · Maple Country, Ltd.Aug 11, 2025Ashton gray — renovation/alteration — tenant improvement · 98 m away
More demolitions in 75201.