Permits cover fire-damage repairs at 3020 Bickers St

Permits filed from Feb. 25 to Apr. 3, 2026, describe repairs to a fire- and water-damaged unit at 3020 Bickers St. The work includes structural and interior repairs, plus HVAC, electrical and plumbing replacement. The records do not identify a tenant or state that a new building is being constructed.

Summarized from City of Dallas records · updated Apr 3, 2026

Projects
4
4 filings
Latest filing
Apr 3, 2026
since Feb 25, 2026
Largest scope
—
Listed value
—

Permit & project history

4 projects
  1. This is for building #22 unit 2232 bath full gut including all new pipe

    This is for building #22 unit 2232 bath full gut including all new pipe

    City of Dallas permitCommercial Plumbing Permit
    Record
    COM-PLM-26-001270
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  2. New hvac and duct work

    New hvac and duct work

    City of Dallas permitCommercial Mechanical Permit
    Record
    COM-MEC-26-000681
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  3. Electrical for remodel

    Electrical for remodel

    City of Dallas permitCommercial Electrical Permit
    Record
    COM-ELC-26-001047
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  4. Mcr 1. structural and framing• replace all fire-damaged structural members and framing components identified in the inspection report.• structural engineer’s design package will be provided by dha; contractor shall implement all specified structural repairs in accordance with engineer’s recommendations.• replace all ceiling joists, studs, sheathing, or structural elements as required to achieve sound framing.• restore roof truss system in accordance with engineer’s repair detail.• repair or replace decking and roof sheathing as needed.2. roofing• replace or repair roof decking, trusses, and shingles affected by fire or water damage.• provide underlayment, flashing, drip edges, and all required accessories.• roofing system to be warranted and installed in accordance with manufacturer specifications and city of dallas code.3. mechanical (hvac)? replace all fire and smoke-damaged ductwork, insulation, air handler, and associatedhvac components.? replace supply and return grilles throughout the unit.? verify full functionality of system upon completion.? all hvac work must be performed under the supervision of a licensed mechanicalcontractor and meet current energy code standards.4. electrical? remove all compromised electrical wiring, rough-in, and devices.? provide new wiring, panels, breakers, devices, switches, and receptacles throughout.? replace all light fixtures, trims, and cover plates.? install combination smoke and carbon monoxide detectors per dallas fire code.? upgrade electrical service to meet current nfpa and nec standards, including gfci andafci protection.? work to be completed under a licensed electrician.5. plumbing? inspect and replace all affected vent piping, drains, and water lines as necessary.? verify no cross-contamination or damage from heat exposure.? replace fixtures (toilets, lavatories, tubs, faucets) and drains in all bathrooms and kitchen.? all plumbing work shall comply with the city of dallas plumbing code and be performed bya licensed plumber.6. interior finishes and fixtures (ffe)? replace all interior doors, trims, baseboards, and casings (not salvageable per report).? replace or repair glazing—only 30% deemed salvageable per inspection report.? replace all gypsum wallboard (60% replacement minimum based on 40% salvageablerating).? provide new texture and paint to match dha’s standard heavy orange peel finish on wallsand popcorn texture on ceilings.? replace all flooring materials throughout the unit.? replace all cabinetry, countertops, and shelving—none are salvageable.• replace all major appliances with new dha-specified energy star units (refrigerator, stove, vent hood).• replace all finish fixtures, mirrors, vent fans, towel bars, and light trims.• replace attic and wall insulation (blown insulation not salvageable).• all paint and coatings to be low-voc and approved by dha prior to installation.7. smoke and water remediation• perform comprehensive smoke and soot remediation throughout all areas of unit 223, including structure, mechanical spaces, and surfaces.• perform water damage remediation throughout affected areas.• provide air scrubbing, odor removal, and hepa vacuuming as necessary.• all remediation work must be inspected and approved by dha before new finishes or insulation are installed.8. site and exterior• clean and pressure wash/acid wash all exterior masonry, fascia, and gutters to remove smoke and soot staining.• restore any exterior components damaged by firefighting operations.• ensure all windows and doors are replaced or repaired to meet energy code and dha standards

    Mcr 1. structural and framing• replace all fire-damaged structural members and framing components identified in the inspection report.• structural engineer’s design package will be provided by dha; contractor shall implement all specified structural repairs in accordance with engineer’s recommendations.• replace all ceiling joists, studs, sheathing, or structural elements as required to achieve sound framing.• restore roof truss system in accordance with engineer’s repair detail.• repair or replace decking and roof sheathing as needed.2. roofing• replace or repair roof decking, trusses, and shingles affected by fire or water damage.• provide underlayment, flashing, drip edges, and all required accessories.• roofing system to be warranted and installed in accordance with manufacturer specifications and city of dallas code.3. mechanical (hvac)? replace all fire and smoke-damaged ductwork, insulation, air handler, and associatedhvac components.? replace supply and return grilles throughout the unit.? verify full functionality of system upon completion.? all hvac work must be performed under the supervision of a licensed mechanicalcontractor and meet current energy code standards.4. electrical? remove all compromised electrical wiring, rough-in, and devices.? provide new wiring, panels, breakers, devices, switches, and receptacles throughout.? replace all light fixtures, trims, and cover plates.? install combination smoke and carbon monoxide detectors per dallas fire code.? upgrade electrical service to meet current nfpa and nec standards, including gfci andafci protection.? work to be completed under a licensed electrician.5. plumbing? inspect and replace all affected vent piping, drains, and water lines as necessary.? verify no cross-contamination or damage from heat exposure.? replace fixtures (toilets, lavatories, tubs, faucets) and drains in all bathrooms and kitchen.? all plumbing work shall comply with the city of dallas plumbing code and be performed bya licensed plumber.6. interior finishes and fixtures (ffe)? replace all interior doors, trims, baseboards, and casings (not salvageable per report).? replace or repair glazing—only 30% deemed salvageable per inspection report.? replace all gypsum wallboard (60% replacement minimum based on 40% salvageablerating).? provide new texture and paint to match dha’s standard heavy orange peel finish on wallsand popcorn texture on ceilings.? replace all flooring materials throughout the unit.? replace all cabinetry, countertops, and shelving—none are salvageable.• replace all major appliances with new dha-specified energy star units (refrigerator, stove, vent hood).• replace all finish fixtures, mirrors, vent fans, towel bars, and light trims.• replace attic and wall insulation (blown insulation not salvageable).• all paint and coatings to be low-voc and approved by dha prior to installation.7. smoke and water remediation• perform comprehensive smoke and soot remediation throughout all areas of unit 223, including structure, mechanical spaces, and surfaces.• perform water damage remediation throughout affected areas.• provide air scrubbing, odor removal, and hepa vacuuming as necessary.• all remediation work must be inspected and approved by dha before new finishes or insulation are installed.8. site and exterior• clean and pressure wash/acid wash all exterior masonry, fascia, and gutters to remove smoke and soot staining.• restore any exterior components damaged by firefighting operations.• ensure all windows and doors are replaced or repaired to meet energy code and dha standards

    City of Dallas permitCommercial Alteration Addition Permit
    Record
    COM-ALT-ADD-26-000363
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro

Sources: City of Dallas

Questions about 3020 Bickers St

What is being built at 3020 Bickers St in Dallas?

The permits describe repairs to a fire- and water-damaged unit, not a new building. The work includes structural repairs, interior replacement and updates to plumbing, electrical and HVAC systems.

When were permits filed for work at 3020 Bickers St?

The four City of Dallas permits in the records were filed from Feb. 25 through Apr. 3, 2026.

What does the alteration permit at 3020 Bickers St cover?

Permit COM-ALT-ADD-26-000363, filed Feb. 25, 2026, describes repairs to fire- and water-damaged structural elements, roofing, mechanical and electrical systems, plumbing and interior finishes.

Are there new plumbing permits for 3020 Bickers St?

Yes. Permit COM-PLM-26-001270, filed Apr. 3, 2026, describes a full gut of a bathroom in building 22, unit 2232, including new piping.

What HVAC and electrical work is permitted at 3020 Bickers St?

A commercial mechanical permit filed Mar. 16, 2026, describes new HVAC and ductwork. A commercial electrical permit filed Mar. 10, 2026, is for electrical work for a remodel.

Is a restaurant opening at 3020 Bickers St?

The records provided do not identify a tenant or say that a restaurant is opening. The permit descriptions focus on repairs and system replacement.

Also being built nearby

All of 75212

More restaurants in 75212.

Get alerts for 3020 Bickers St