9440 Garland Rd
Dallas, TX 75218
Interior finish-out permitted at 9440 Garland Road
A Qteam QR interior finish-out of an existing space was permitted at 9440 Garland Road on January 15, 2026. Dallas permits also cover related electrical work, a bottle filler and gas test, and new ductwork, filed January 21, January 29, and February 5.
Summarized from City of Dallas, Texas Department of Licensing and Regulation records · updated Feb 5, 2026
- Projects
- 21
- 21 filings
- Latest filing
- Feb 5, 2026
- since Dec 24, 2020
- Largest scope
- —
- Estimated cost
- $80K
- state registration
Where this project stands
CompletedGlo Tanning - Casa Linda Plaza
2,317 sq ft · $80K est.
- RegisteredMay 5, 2023
- Plan review
- ConstructionMay '23 – Jun '23
- Inspected
- Closed
Ran as a 1-month build.
4 contacts on this project · 2 phone numbers
Permit & project history
21 projectsInterior finish out of tenant space — glo tanning
TDLR project registrationRenovation/AlterationProject Closed2,317 sq ft$80K est.- Project #
- TABS2023018425
- Tenant / owner
- Glo Tanning - Casa Linda Plaza
- Design firm
- Pro
- Contact
- Pro
Sources: City of Dallas · Texas Department of Licensing and Regulation
Questions about 9440 Garland Rd
What is being built at 9440 Garland Road?
City of Dallas permits describe an interior finish-out of an existing space for Qteam QR. Related permits cover electrical, plumbing, and mechanical work.
When were permits filed for 9440 Garland Road?
The finish-out permit, COM-ALT-ADD-26-000020, was filed January 15, 2026. Related electrical, plumbing, and mechanical permits were filed from January 21 through February 5.
What work is included in the 9440 Garland Road permits?
The permits describe an interior finish-out, associated electrical work, installation of a bottle filler and a gas test, and new ductwork.
What's being built near Chase Casa Linda - Relo Redev?
At 9440 Garland Road, 42 meters from the Chase Casa Linda - Relo Redev address listed in the records, permits describe an interior finish-out of an existing space. The records do not identify the space's use.
Is a new business opening at 9440 Garland Road?
The permits describe a Qteam QR interior finish-out of an existing space, but do not state an opening date or identify a business use.
Also being built nearby
All of 75218- 9440 Garland Road · Reformed PilatesJan 5, 2026Reformed pilates — renovation/alteration — interior finish-out of existing lease space. existing and new electrical, mechanical and plumbing equipment
- 9409 Garland RdNov 4, 2026New construction of a 1 story retail bank, 3569 sq ft @ standalone drive up atm's · 42 m away
- 9409 Garland Road · Jpmorgan Chase Bank, N.a.Oct 29, 2026Chase casa linda - relo redev — new construction — new construction of a 1-story retail banking center (3,659 sq ft) with (2) remote freestanding drive-up atm's · 42 m away
- 9371 Garland RdFeb 23, 2026Service release no work · 88 m away
- 9365 Garland RdSep 8, 2026New main circuit breaker and generator with ats · 94 m away
- 9343 Garland RdJan 28, 2021Install swimming pool · 116 m away
- 9335 Garland RdNov 5, 2025Repair gas line · 124 m away
- 9412 Forest Hills BlvdJan 1, 2026Gas test · 128 m away
- 1151 N Buckner BlvdJul 8, 2026Commercial remodel · 151 m away
- 9352 Angora StSep 24, 2025Gas test using air pressure. the property is a duplex, but since we are doing only one unit, i registered the permit as a residential single family. this is the way the buildng inspection office told me to do so i wouldn't get charged for two units of the duplex residence · 153 m away
- 9331 Angora StJun 9, 202626kw kohler generator installation · 182 m away
- 9326 Angora StSep 29, 2025We will then tunnel approximately 50ft under home to expose old cast iron sewer lines. we will then remove old cast iron and replace with schedule 40 pvc. bid also includes running a new water main from the front yard towards the home. will add a homeowner shut off valve before entering crawlspace. includes all new water connections through the floor. this includes both bathrooms, kitchen and washer** scope change **we will be replacing the entire sewer line and we are going to be replacing two fifty gallon water heaters with new units as well. the sewer line portion will be replaced with brand new schedule 40 pvc · 206 m away