New electric meters planned for four buildings on Webb Chapel Ext

Four City of Dallas permits indicate new 800-amp utility meter transockets for the four buildings at 2555 Webb Chapel Ext. The permits were filed November 11 and 18, 2025, and describe rerouting existing electrical service conductors through the new meters to existing main breaker disconnects.

Summarized from City of Dallas records · updated Nov 18, 2025

Projects
4
4 filings
Latest filing
Nov 18, 2025
since Nov 11, 2025
Largest scope
—
Listed value
—

Permit & project history

4 projects
  1. Building 1we are installing a new 800a utility meter transocket. 1. existing overhead utility service conductors are landed into an existing 800a main breaker disconnect. 2. we are removing existing service conductors from the 800a disconnect and landing them into the line side of new utility meter transocket. 3. we will then run conductors from load side of new utility transocket back to the 800a main breaker disconnect.we have 4 buildings at this property and will file a permit for each building, as oncor has created a new main electric meter address for each building

    Building 1we are installing a new 800a utility meter transocket. 1. existing overhead utility service conductors are landed into an existing 800a main breaker disconnect. 2. we are removing existing service conductors from the 800a disconnect and landing them into the line side of new utility meter transocket. 3. we will then run conductors from load side of new utility transocket back to the 800a main breaker disconnect.we have 4 buildings at this property and will file a permit for each building, as oncor has created a new main electric meter address for each building

    City of Dallas permitCommercial Electrical Permit
    Record
    COM-ELC-25-003066
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  2. Building 4we are installing a new 800a utility meter transocket. 1. existing overhead utility service conductors are landed into an existing 800a main breaker disconnect.2. we are removing existing service conductors from the 800a disconnect and landing them into the line side of new utility meter transocket. 3. we will then run conductors from load side of new utility transocket back to the 800a main breaker disconnect. we have 4 buildings at this property and will file a permit for each building, as oncor has created a new main electric meter address for each building.this is application for building 4 and will need inspection to restore power for oncor utility

    Building 4we are installing a new 800a utility meter transocket. 1. existing overhead utility service conductors are landed into an existing 800a main breaker disconnect.2. we are removing existing service conductors from the 800a disconnect and landing them into the line side of new utility meter transocket. 3. we will then run conductors from load side of new utility transocket back to the 800a main breaker disconnect. we have 4 buildings at this property and will file a permit for each building, as oncor has created a new main electric meter address for each building.this is application for building 4 and will need inspection to restore power for oncor utility

    City of Dallas permitCommercial Electrical Permit
    Record
    COM-ELC-25-003077
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  3. Building 3we are installing a new 800a utility meter transocket. 1. existing overhead utility service conductors are landed into an existing 800a main breaker disconnect.2. we are removing existing service conductors from the 800a disconnect and landing them into the line side of new utility meter transocket. 3. we will then run conductors from load side of new utility transocket back to the 800a main breaker disconnect. we have 4 buildings at this property and will file a permit for each building, as oncor has created a new main electric meter address for each building.this is application for building 3 we will need inspection to restore service

    Building 3we are installing a new 800a utility meter transocket. 1. existing overhead utility service conductors are landed into an existing 800a main breaker disconnect.2. we are removing existing service conductors from the 800a disconnect and landing them into the line side of new utility meter transocket. 3. we will then run conductors from load side of new utility transocket back to the 800a main breaker disconnect. we have 4 buildings at this property and will file a permit for each building, as oncor has created a new main electric meter address for each building.this is application for building 3 we will need inspection to restore service

    City of Dallas permitCommercial Electrical Permit
    Record
    COM-ELC-25-003076
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  4. Building 2we are installing a new 800a utility meter transocket. 1. existing overhead utility service conductors are landed into an existing 800a main breaker disconnect.2. we are removing existing service conductors from the 800a disconnect and landing them into the line side of new utility meter transocket. 3. we will then run conductors from load side of new utility transocket back to the 800a main breaker disconnect. we have 4 buildings at this property and will file a permit for each building, as oncor has created a new main electric meter address for each building.this is application for building 2

    Building 2we are installing a new 800a utility meter transocket. 1. existing overhead utility service conductors are landed into an existing 800a main breaker disconnect.2. we are removing existing service conductors from the 800a disconnect and landing them into the line side of new utility meter transocket. 3. we will then run conductors from load side of new utility transocket back to the 800a main breaker disconnect. we have 4 buildings at this property and will file a permit for each building, as oncor has created a new main electric meter address for each building.this is application for building 2

    City of Dallas permitCommercial Electrical Permit
    Record
    COM-ELC-25-003075
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro

Sources: City of Dallas

Questions about 2555 Webb Chapel Ext

What is being built at 2555 Webb Chapel Ext?

City permits describe installation of new 800-amp utility meter transockets for four buildings at the property. The work uses existing electrical service conductors and main breaker disconnects.

When were permits filed for 2555 Webb Chapel Ext?

The City of Dallas filed three permits on November 11, 2025, and one on November 18, 2025. The permits are COM-ELC-25-003075, COM-ELC-25-003076, COM-ELC-25-003077 and COM-ELC-25-003066.

Is a new building planned at 2555 Webb Chapel Ext?

The permits describe electrical meter work for four buildings at the property, not construction of a new building.

What electrical work is planned at 2555 Webb Chapel Ext?

The permits describe moving existing overhead service conductors to the line side of new 800-amp meter transockets, then running conductors back to the existing main breaker disconnects.

What's happening near Carniceria Prime on Webb Chapel Ext?