Ava Apartments foundation and building-system repairs
Dallas permits show foundation repairs at Ava Apartments buildings 13, 18 and 24, with filings dated May 7 and May 14, 2025. Later permits cover electrical, plumbing and boiler work at the address, including a boiler replacement filed October 21, 2026; the records do not indicate new construction.
Summarized from City of Dallas records · updated Oct 21, 2026
- Projects
- 8
- 8 filings
- Latest filing
- Oct 21, 2026
- since Nov 17, 2020
- Largest scope
- —
- Listed value
- $1
- partial · often understated
Permit & project history
8 projectsThe current boiler system adjacent to building 8 is non-operational due to the fire box burning through the back, necessitating replacement to restore reliable function and address heating and water needs.we recommend replacing the existing boiler system with a new ray pack boiler, accompanied by a single-story vent package, a 200-gallon storage tank, and an optimized pump assembly utilizing copper components. additionally, new water valves will be installed in the boiler room, and our team will ensure the removal of the old system after installation. - guarantees efficient operation and enhanced system reliability.- addresses safety concerns and improves long-term performance
The current boiler system adjacent to building 8 is non-operational due to the fire box burning through the back, necessitating replacement to restore reliable function and address heating and water needs.we recommend replacing the existing boiler system with a new ray pack boiler, accompanied by a single-story vent package, a 200-gallon storage tank, and an optimized pump assembly utilizing copper components. additionally, new water valves will be installed in the boiler room, and our team will ensure the removal of the old system after installation. - guarantees efficient operation and enhanced system reliability.- addresses safety concerns and improves long-term performance
City of Dallas permitCommercial Plumbing PermitUnit 2605 building 20not getting proper voltage to unit 2065 in building 20 due to interior meter bank components are burning up and needing replaced.-- location of replacement parts. -- before starting any repairs, contact oncor to get a disconnect and reconnect order and receive an e.t.a. after receiveing e.t.a from oncor. contact city for "stand alone" permit and schedule same day inspection. -- safely remove and replace thr burned/damaged interior components of the meter bank. ensure all work complies with current city electrical codes.-- perform all testing to verify correct operation of meter bank.-- call in for inspection and reconnection
Unit 2605 building 20not getting proper voltage to unit 2065 in building 20 due to interior meter bank components are burning up and needing replaced.-- location of replacement parts. -- before starting any repairs, contact oncor to get a disconnect and reconnect order and receive an e.t.a. after receiveing e.t.a from oncor. contact city for "stand alone" permit and schedule same day inspection. -- safely remove and replace thr burned/damaged interior components of the meter bank. ensure all work complies with current city electrical codes.-- perform all testing to verify correct operation of meter bank.-- call in for inspection and reconnection
City of Dallas permitCommercial Electrical PermitAva apartments- building. 24- foundation repair- installing 35 exterior pilings & 8 interior pilingsfoundation repair onlyno plan review requiredfoundation repair only, no layout changes allowed.all work subject to field inspector approval. foundation repair only, no layout changes allowed
Ava apartments- building. 24- foundation repair- installing 35 exterior pilings & 8 interior pilingsfoundation repair onlyno plan review requiredfoundation repair only, no layout changes allowed.all work subject to field inspector approval. foundation repair only, no layout changes allowed
City of Dallas permitCommercial Foundation RepairAva apartments building. 18- foundation repair- installing 33 exterior & 2 interior pilingsfoundation repair onlyno plan review requiredfoundation repair only, no layout changes allowed.all work subject to field inspector approval. foundation repair only, no layout changes allowed
Ava apartments building. 18- foundation repair- installing 33 exterior & 2 interior pilingsfoundation repair onlyno plan review requiredfoundation repair only, no layout changes allowed.all work subject to field inspector approval. foundation repair only, no layout changes allowed
City of Dallas permitCommercial Foundation RepairAva apartments- building. 13- foundation repair- installing 43 exterior pilings & 18 interior pilings
Ava apartments- building. 13- foundation repair- installing 43 exterior pilings & 18 interior pilings
City of Dallas permitCommercial Foundation Repair
Sources: City of Dallas
Questions about 8401 Skillman St
What is being built at 8401 Skillman St?
The permits do not indicate a new building. They document foundation repairs at Ava Apartments and later work on building systems.
Are the permits for new apartments at 8401 Skillman St?
No new apartment construction is described in these records. Foundation repair permits were filed for Ava Apartments buildings 13, 18 and 24 in May 2025.
What foundation work is planned at Ava Apartments?
Permits describe installing pilings at buildings 13, 18 and 24. The filings were dated May 7 and May 14, 2025, and specify foundation repair without layout changes.
When was the boiler replacement permit filed at 8401 Skillman St?
The commercial plumbing permit, COM-PLM-26-004053, was filed October 21, 2026. Its description calls for replacing the non-operational boiler near building 8.
What other repairs are listed for 8401 Skillman St?
The records include replacement of electrical meter-bank components in building 20, filed July 8, 2025, and a backflow-prevention assembly replacement near the office, filed May 13, 2026.
Which Ava Apartments buildings have foundation repair permits?
Permits identify buildings 13, 18 and 24. They were filed May 7, 2025, for buildings 13 and 18, and May 14, 2025, for building 24.
Also being built nearby
All of 75231- 8303 Skillman StNov 21, 2025Gas meter relocate for boiler room · 143 m away
- 9801 Royal LnJun 4, 2025Remove old hvac and replace it with 1.5 ton pancake unit for the upstairs · 181 m away
- 8407 Oak StreamFeb 24, 2026100 ft gas line replacement to new location set by atmos energy · 199 m away
- 9502 Milltrail DrSep 30, 2026Installation of a 11.500 kw ac roof mount pv system with a 13.5 kwh battery · 212 m away
- 9505 Milltrail DrJan 11, 2021Replace water heater & replace/test gas service · 216 m away
- 9910 Royal LnOct 30, 20262 ton pancake straight ac system · 227 m away
- 9608 Robin SongJun 3, 2025Replacing a 4 ton gas complete system · 243 m away
- 9315 Trailhill DrMay 8, 2026Hvac replacement · 249 m away
- 9522 Milltrail DrAug 5, 2025Replacing 5 ton base horizontal gas system · 262 m away
- 9408 Summerhill LnMar 26, 2026200 amp panel and meter base replacement · 270 m away
- 8201 Fair Oaks XingNov 17, 2020Run gas line to firepit · 277 m away
- 9302 Faircrest DrSep 29, 2026Nsfaa resid addition · 282 m away
More apartments & multifamily in 75231, warehouses & industrial in 75231, offices in 75231.