Yard gas line replacement permitted at 8714 Gladwood Ln
A residential plumbing permit covers replacing the yard gas line from the meter to the home at 8714 Gladwood Ln. The City of Dallas permit was filed August 17, 2026; its description says the existing line was not holding pressure and gas to the home was off.
Summarized from City of Dallas records · updated Aug 17, 2026
- Projects
- 1
- 1 filings
- Latest filing
- Aug 17, 2026
- since Aug 17, 2026
- Largest scope
- —
- Listed value
- —
Permit & project history
1 projectReplacement of yard gas line from meter to home. current line is not holding pressure, gas to home is currently off
Replacement of yard gas line from meter to home. current line is not holding pressure, gas to home is currently off
City of Dallas permitResidential Plumbing Permit
Sources: City of Dallas
Questions about 8714 Gladwood Ln
What work is permitted at 8714 Gladwood Ln?
A City of Dallas residential plumbing permit covers replacing the yard gas line from the meter to the home. The permit was filed August 17, 2026.
When was the gas line replacement permit filed?
The permit was filed August 17, 2026. Its number is RES-PLM-26-008657.
Why is the gas line being replaced at 8714 Gladwood Ln?
The permit description says the existing line was not holding pressure. It also says gas to the home was off.
Is a new home being built at 8714 Gladwood Ln?
The record provided is for a residential plumbing permit to replace a yard gas line, not a new-home construction permit.
What does the permit say about the gas service at the home?
The permit description says gas to the home was currently off because the existing yard line was not holding pressure.
Also being built nearby
All of 75243- 8709 Gladwood LnNov 4, 2025Gas repair with test · 15 m away
- 8710 Westfield DrSep 24, 2026Nsfaa **scope of work – 29.5' w x 17' l combo patio cover & concrete****patio cover:**construct a custom 29.5' w x 17' l (392 sq ft) cedar attached patio cover with a gable/low-pitch slant roof, decorative front fascia/trim, and approximately 12' finished top height. customer-provided dimensions are assumed correct; discrepancies requiring additional materials/work will be handled by change order.entire structure to be constructed with cedar, including (4) 6"x6" front/exposed posts (inset 1'), headers, rafters, fascia, trim, pony walls, and tongue-and-groove ceiling. front span supported by up to four posts. include roofline tie-in with approximately 192 sq ft of additional framing, plywood, shingles, and flashing.**structural tie-in:**install new independent concrete footings with commercial-grade simpson brackets for posts. structurally attach patio cover to existing house wall studs for load transfer and lateral stability. bottom of 4"x12" header boards approximately 8.5' high; final elevations depend on existing soffit, windows, ledgers, and roofline.**roofing:**cedar rafters, headers, risers, fascia, and visible trim. install plywood roof decking, full waterproofing/moisture barrier, and 30-year shingles matching the existing home. flash new roof into existing roof on two sides for a weather-tight connection. provide 12" roof overhang on front, left, and far-right sides. **no gutters.****ceiling:**full tongue-and-groove cedar ceiling throughout covered area. homeowner to select available ready seal stain/color. speaker company to complete required speaker wiring before tongue-and-groove ceiling installation.**electrical:**provide one dedicated circuit for outdoor lighting, fan, and outlets, with up to 150' of wiring to breaker panel through attic. includes (6) recessed can lights with switch, placement per homeowner preference; (1) ceiling fan box (homeowner supplies fan; 3 nails living installs); and (2) outdoor outlets.**plans, engineering & permits:**3 nails living to prepare plans/blueprints for city permit submission. homeowner approval of plans, design, and style required before submission. unforeseen structural requirements will be communicated and may result in a change order, including third-party engineering if required.**concrete – 392 sq ft regular brushed concrete:**prepare site by protecting adjacent landscaping/hardscape, removing existing surface/vegetation as needed, hauling debris, and excavating approximately 8–10" below finished grade. install and compact 4–6" crushed stone/base to 95% standard proctor. form slab, install welded wire mesh (6x6 w1.4/w1.4) or rebar as required, and pour approximately 4" of 3000–3500 psi air-entrained concrete. provide control/construction joints per industry standards. finish with broom texture and bullnose or square edges per homeowner preference. remove forms, clean site, and apply two coats of approved sealer after proper cure time (typically 7–28 days). includes excavation, base, reinforcement, concrete, forms, equipment, labor, finishing, jointing, sealing, cleanup, one mobilization, and minor debris disposal.**concrete assumptions:**392 sq ft area; 4" slab thickness unless otherwise specified; 3000–3500 psi concrete subject to local requirements; suitable site access for equipment/material delivery; work subject to weather conditions.**exclusions:**any new concrete/slab extension not specifically included. final stain/sealer color selected by homeowner. additional structural work or engineering required due to unforeseen site/home conditions may be subject to change order.**drainage:**install approximately 85 linear feet of french drain · 119 m away
- 9134 Woodshore DrJun 23, 2025Installing 5 total pilings (2 exterior, 3 breakouts) · 119 m away
- 8631 Westfield DrFeb 9, 2026X1 50 gal gas water heater in the garage in closet · 136 m away
- 9124 Woodshore DrAug 5, 2026Panel change and add smoke detectors · 136 m away
- 8625 Westfield DrFeb 19, 2026Slab leak water repair · 142 m away
- 9120 Woodshore DrJan 20, 2026Gas test and remplaced a valve · 143 m away
- 8619 Westfield DrJan 15, 202625ft main gas re pipe with 4 appliance drops (furnace/wh/stove/dryer) · 149 m away
- 8605 Westfield DrSep 2, 2026Water repair isolated cold water leak · 164 m away
- 8612 Hanford DrAug 21, 2026Remove & replace shingles · 172 m away
- 8810 Hanford DrSep 23, 2025Installation of circuits for plugs and lights in living room · 172 m away
- 8606 Hanford DrSep 10, 2026Removed and replace the hvac system. equipment only · 179 m away