919 Hunter Dr
El Paso, TX 79915 · Restroom Renovation At Building "c" - Valle Verde Campus, New Elevator Tower And Interior Renovation - Building C + 2 more
Elevator additions and restroom renovation at Valle Verde Campus
TDLR registrations indicate elevator additions in Buildings A, B and C and restroom work in Building C at the multi-tenant campus site. The filings were dated September 26, 2024, for Buildings A and B; October 24, 2024, for Building C’s elevator; and June 16, 2025, for the restroom renovation.
Summarized from Texas Department of Licensing and Regulation records · updated Jun 16, 2025
- Projects
- 4
- 4 filings
- Latest filing
- Jun 16, 2025
- since Sep 26, 2024
- Largest scope
- 890 sf
- Estimated cost
- $3.3M
- state registration
Where this project stands
Inspected · closing outRestroom Renovation at Building "C" - Valle Verde Campus
890 sq ft · $350K est.
- RegisteredJun 16, 2025
- Plan review
- ConstructionJul '25 – Dec '25
- Inspected
- Closednow
The building is substantially done. Move-in, fit-out and service work usually follow.
4 contacts on this project · 3 phone numbers
Permit & project history
4 projectsExisting restroom renovation and new family restroom. — building "c
TDLR project registrationRenovation/AlterationInspection Complete890 sq ft$350K est.- Project #
- TABS2025021368
- Tenant / owner
- Restroom Renovation At Building "c" - Valle Verde Campus
- Design firm
- Pro
- Contact
- Pro
New elevator tower and renovation of required areas to incorporate the new elevator tower. — el paso community college building c
TDLR project registrationAdditions to Existing BuildingReview Complete440 sq ft$3.3M est.- Project #
- TABS2025003976
- Tenant / owner
- New Elevator Tower And Interior Renovation - Building C
- Design firm
- Pro
- Contact
- Pro
Addition of two elevators to existing building and vestibule — epcc - valle verde campus building. b
TDLR project registrationAdditions to Existing BuildingReview Complete440 sq ft$1.3M est.- Project #
- TABS2025001943
- Tenant / owner
- Valle Verde Campus - Building B - New Elevator Tower
- Design firm
- Pro
- Contact
- Pro
Addition of two elevators to existing buildings — epcc - valle verde campus building. a
TDLR project registrationAdditions to Existing BuildingReview Complete400 sq ft$1.1M est.- Project #
- TABS2025001942
- Tenant / owner
- Valle Verde Campus - Building A - New Elevator Tower
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 919 Hunter Dr
What is being built at 919 Hunter Drive in El Paso?
TDLR registrations describe elevator additions to campus Buildings A, B and C, along with a Building C restroom renovation and new family restroom. The filings date from September 2024 through June 2025.
What is being built at El Paso Community College near 919 Hunter Drive?
The registrations cover elevator work in Buildings A, B and C at the Valle Verde Campus, plus restroom renovations in Building C. The Building A and B elevator filings were dated September 26, 2024.
Are new elevators being added at Valle Verde Campus?
Yes. TDLR filings describe elevator additions in Buildings A, B and C. The Building C filing, dated October 24, 2024, also includes an elevator tower and related interior renovation.
What restroom work is planned for Building C at Valle Verde Campus?
A TDLR registration dated June 16, 2025, describes renovation of an existing restroom and a new family restroom in Building C. Its listed status is Inspection Complete.
When were the Valle Verde Campus elevator projects filed?
The Building A and Building B elevator filings were dated September 26, 2024. The Building C elevator tower and interior renovation filing was dated October 24, 2024.
Are the Valle Verde Campus elevator projects complete?
The TDLR registrations for the Building A and B elevator additions and the Building C elevator tower are listed as Review Complete. That status alone does not establish that construction is finished.