2723 East US Highway 290
Fort Stockton, TX 79735 · Loves Travel Stop #542
Four EV charging stations planned at Love’s #542 in Fort Stockton
A project registration describes installing four electric vehicle charging stations, a power cabinet and 2,000-amp electrical switchgear at Love’s Travel Stop #542, 2723 East US Highway 290. The Texas Department of Licensing and Regulation filing was dated October 22, 2026, and lists an applicant-estimated project cost of $600,000.
Summarized from Texas Department of Licensing and Regulation records · updated Oct 22, 2026
- Projects
- 2
- 2 filings
- Latest filing
- Oct 22, 2026
- since Feb 3, 2025
- Largest scope
- 31,000 sf
- Estimated cost
- $600K
- state registration
Where this project stands
Approved · construction starts Mar 1, 2027Love's 542 EV Charging Station -Fort Stockton, TX
1,905 sq ft · $600K est.
- RegisteredOct 22, 2026
- Plan review
- ConstructionMar '27 – Apr '27
- Inspected
- Closed
A 2-month build is scheduled. Bids for subcontractors and suppliers usually close before the start date.
4 contacts on this project · 3 phone numbers
Permit & project history
2 projectsInstallation of four single electric vehicle charging stations, one power cabinet, one 2000a electrical switchgear. — loves travel stop #542
TDLR project registrationRenovation/AlterationReview Complete1,905 sq ft$600K est.- Project #
- TABS2027004181
- Tenant / owner
- Pro
- Design firm
- Pro
- Contact
- Pro
Add overnight rv parking spaces with utility hookups and relocate dog park — love's travel stop #542
TDLR project registrationRenovation/AlterationProject Closed31,000 sq ft$550K est.- Project #
- TABS2025010966
- Tenant / owner
- Love's Travel Stop #542 Rv Parking Addition
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 2723 East US Highway 290
What is being built at 2723 East US Highway 290 in Fort Stockton?
A TDLR project registration describes four electric vehicle charging stations, a power cabinet and electrical switchgear at Love’s Travel Stop #542. The filing is dated October 22, 2026.
Is Love’s adding EV chargers in Fort Stockton?
A project registration for Love’s Travel Stop #542 describes installing four single electric vehicle charging stations. It is listed as a renovation or alteration.
How many EV charging stations are planned at Love’s #542?
The TDLR registration describes four single electric vehicle charging stations at 2723 East US Highway 290.
How much will the Fort Stockton EV charging project cost?
The TDLR filing lists an applicant-estimated cost of $600,000 for the project. This is an estimate, not a confirmed final cost.
When was the Love’s #542 charging project filed?
The TDLR project registration was dated October 22, 2026. Its project number is TABS2027004181.
Has the Love’s #542 EV charging project been approved?
The TDLR record lists the project status as “Review Complete.” The filing describes the planned installation but does not state when the chargers will be installed.