groundranger
Historic · latest filing Apr 2024Commercial

3100 N Terminal Blvd

Houston, TX 77032 · Terminal B Redovelopment - Priority Walls, Terminal B Temporary Kcm Lane

Terminal B work adds back-of-house rooms and temporary check-in

TDLR registrations describe new walls and doors for back-of-house rooms and a temporary security check-in at the multi-tenant Terminal B site. The projects were filed March 14 and April 23, 2024.

Summarized from Texas Department of Licensing and Regulation records · updated Apr 23, 2024

Projects
2
2 filings
Latest filing
Apr 23, 2024
since Mar 14, 2024
Largest scope
14,640 sf
Estimated cost
$250K
state registration

Where this project stands

Finishing up · inspection next

Terminal B Redovelopment - Priority Walls

14,640 sq ft · $250K est.

  1. RegisteredApr 23, 2024
  2. Plan review
  3. ConstructionNov '24 – Nov '25
  4. Inspectednow
  5. Closed

Scheduled to finish Nov 3, 2025; the state inspection hasn't been filed yet.

4 contacts on this project · 2 phone numbers

Permit & project history

2 projects
  1. New walls and doors for new boh rooms. steel fireproofing, extension to existing stairs, thermal insulation, and wall rough in for prep for future work electrical, telecom/security installation. — iah terminal b

    TDLR project registrationRenovation/AlterationReview Complete14,640 sq ft$250K est.
    Tenant / owner
    Terminal B Redovelopment - Priority Walls
    Design firm
    Pro
    Contact
    Pro
  2. New walls and doors for temporary security check-in — iah terminal b

    TDLR project registrationRenovation/AlterationProject Closed250 sq ft$50K est.
    Tenant / owner
    Terminal B Temporary Kcm Lane
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 3100 N Terminal Blvd

What is being built at 3100 N Terminal Blvd?

TDLR registrations describe back-of-house rooms with new walls and doors, plus a temporary security check-in area. Both projects are renovations or alterations at Terminal B.

When were the Terminal B projects permitted?

The TDLR registration for the temporary security check-in was filed March 14, 2024 (TABS2024013847). The back-of-house work was filed April 23, 2024 (TABS2024016821).

What is the back-of-house work at IAH Terminal B?

The April 23, 2024 registration describes new walls and doors for back-of-house rooms, steel fireproofing, an extension to existing stairs, and preparation for future electrical and telecom/security work. The registration lists 14,640 square feet.

Is there a temporary security check-in planned for Terminal B?

A TDLR registration filed March 14, 2024 describes new walls and doors for a temporary security check-in. The project registration is TABS2024013847.

What's being built near United Airlines at Terminal B?

The records describe Terminal B renovations for back-of-house rooms and a temporary security check-in, not a project attributed to United Airlines. The nearby United Airlines listing is at Terminal B, Level 3.

What's happening near George Bush Intercontinental Airport?

At the airport's Terminal B, TDLR records describe two renovation projects filed in March and April 2024: a temporary security check-in area and back-of-house rooms.