Port Arthur Fire Station No. 2 planned at 700 Rev. Raymond Scott Ave.
A new 15,457-square-foot fire station with surrounding site work and parking is planned at 700 Rev. Raymond Scott Ave. The project was registered with the Texas Department of Licensing and Regulation on June 17, 2026; its listed status is Review Complete.
Summarized from Texas Department of Licensing and Regulation records · updated Jun 17, 2026
- Projects
- 1
- 1 filings
- Latest filing
- Jun 17, 2026
- since Jun 17, 2026
- Largest scope
- 15,457 sf
- Estimated cost
- $11M
- state registration
Where this project stands
Under constructionPort Arthur Fire Station No. 2
15,457 sq ft · $11M est.
- RegisteredJun 17, 2026
- Plan review
- ConstructionAug '26 – Aug '27
- Inspected
- Closed
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectNew fire station and surrounding site and parking — port arthur fire station no. 2
TDLR project registrationNew ConstructionReview Complete15,457 sq ft$11M est.- Project #
- TABS2026023109
- Tenant / owner
- Port Arthur Fire Station No. 2
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 700 Rev. Raymond Scott Ave., Port Arthur, TX 77640
What is being built at 700 Rev. Raymond Scott Ave. in Port Arthur?
A new fire station, including surrounding site work and parking, is planned for the address. The project is named Port Arthur Fire Station No. 2.
Where is Port Arthur Fire Station No. 2 being built?
The project is listed at 700 Rev. Raymond Scott Ave., Port Arthur, TX 77640.
When was the Port Arthur Fire Station No. 2 project filed?
The Texas Department of Licensing and Regulation project registration is dated June 17, 2026.
How large will the new Port Arthur fire station be?
The project registration lists a size of 15,457 square feet.
What is the estimated cost of Port Arthur Fire Station No. 2?
The TDLR registration lists an estimated project cost of $11.25 million. This is the applicant's estimate.
Has the Port Arthur Fire Station No. 2 project been approved?
The TDLR registration lists the project status as Review Complete. The record does not provide further approval details.