New Magnolia Beach volunteer fire station planned

Plans call for demolishing the existing fire station and parking facilities at 873 Margie Tewmey Road and building a new fire station with parking. The 6,060-square-foot project was registered with the Texas Department of Licensing and Regulation on December 1, 2025. The applicant estimates the project will cost $2.4 million.

Summarized from Texas Department of Licensing and Regulation records · updated Dec 1, 2025

Projects
1
1 filings
Latest filing
Dec 1, 2025
since Dec 1, 2025
Largest scope
6,060 sf
Estimated cost
$2.4M
state registration

Where this project stands

Under construction

GLO MIT-MOD Contract No. 24-065-152-F011 & FEMA Project No. DR-4485-0067

6,060 sq ft · $2.4M est.

  1. RegisteredDec 1, 2025
  2. Plan review
  3. ConstructionMar '26 – Mar '27
  4. Inspected
  5. Closed
72% through of a 12-month buildMar 1, 2026 → Mar 1, 2027

4 contacts on this project · 4 phone numbers

Permit & project history

1 project
  1. Demolition existing fire station building and parking, install new fire station and parking facilities. new building to be 6,060 sq ft — magnolia beach volunteer fire department

    TDLR project registrationNew ConstructionReview Complete6,060 sq ft$2.4M est.
    Tenant / owner
    Glo Mit-Mod Contract No. 24-065-152-F011 & Fema Project No. Dr-4485-0067
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 873 Margie Tewmey Road

What is being built at 873 Margie Tewmey Road?

Plans call for a new 6,060-square-foot fire station and parking facilities, replacing the existing station and parking. The project registration identifies the Magnolia Beach Volunteer Fire Department.

Is the existing fire station being demolished?

Yes. The project description says the existing fire station building and parking will be demolished before the new facilities are installed.

How big will the new fire station be?

The TDLR registration lists the new building at 6,060 square feet.

When was the fire station project filed?

The project was registered with the Texas Department of Licensing and Regulation on December 1, 2025. Its registration number is TABS2026006957.

How much will the new fire station cost?

The applicant’s estimated cost for the project is $2.4 million. This is an estimate, not a confirmed final project cost.

Has construction started on the new fire station?

The TDLR record lists the project status as “Review Complete.” It does not provide a construction start date.