105 Auditorium Cir
San Antonio, TX 78205 · 9th & 11th Floor Aon Renovation, 8th Floor Renovation
Office renovations planned at 105 Auditorium Circle
Two interior renovation projects are listed for this multi-tenant building: an 8th-floor renovation and work on the 9th and 11th floors for telecom racks and electrical and HVAC systems. The 8th-floor project was registered on March 5, 2026, and the 9th- and 11th-floor project was registered on May 6, 2026.
Summarized from Texas Department of Licensing and Regulation records · updated May 6, 2026
- Projects
- 2
- 2 filings
- Latest filing
- May 6, 2026
- since Mar 5, 2026
- Largest scope
- 13,776 sf
- Estimated cost
- $8.0M
- state registration
Where this project stands
In state plan review9th & 11th floor AON renovation
13,776 sq ft · $8.0M est.
- RegisteredMay 6, 2026
- Plan reviewnow
- ConstructionJun '26 – May '27
- Inspected
- Closed
Design is filed with the state. Subcontractors and suppliers are usually picked around now.
4 contacts on this project · 3 phone numbers
Permit & project history
2 projectsThe development of a “white space” for installation of new telecom racks on the 9th floor and addition of hvac and electrical system to serve the room. on the 11th floor, the existing open space will be utilized to house new electrical substation, an — 105 auditorium cir
TDLR project registrationRenovation/AlterationProject Registered13,776 sq ft$8.0M est.- Project #
- TABS2026019620
- Tenant / owner
- 9th & 11th Floor Aon Renovation
- Design firm
- Pro
- Contact
- Pro
Renovation including the demolition of doors, walls, ceilings, lighting, and flooring and the addition of new walls, doors, ceilings, lighting, power, paint, and flooring. — 105 auditorium cir
TDLR project registrationRenovation/AlterationProject Closed8,340 sq ft$220K est.- Project #
- TABS2026014212
- Tenant / owner
- 8th Floor Renovation
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 105 Auditorium Cir
What is being built at 105 Auditorium Circle?
Two office renovation projects are listed at the multi-tenant building: one on the 8th floor and another on the 9th and 11th floors. The latter includes a room for telecom racks and an electrical substation.
What work is planned on the 9th and 11th floors at 105 Auditorium Circle?
The project registration describes a 9th-floor space for new telecom racks, with HVAC and electrical systems, and an 11th-floor electrical substation. It was registered May 6, 2026, as TABS2026019620.
What is included in the 8th-floor renovation at 105 Auditorium Circle?
The registration describes removing and replacing interior doors, walls, ceilings, lighting, and flooring, along with adding power and paint. The project was registered March 5, 2026, as TABS2026014212.
When were renovations filed for 105 Auditorium Circle?
The 8th-floor renovation was registered March 5, 2026. The 9th- and 11th-floor renovation was registered May 6, 2026.
Is all of 105 Auditorium Circle being renovated for Aon?
The records describe a multi-tenant building and list separate renovation projects by floor. One project is named “9th & 11th floor AON renovation”; the records do not say the whole address is for Aon.
What renovations are planned near Visit San Antonio in San Antonio?
At 105 Auditorium Circle, about 357 meters from Visit San Antonio at 112 E. Pecan Street, records list renovations on the 8th, 9th, and 11th floors. The two project registrations are dated March 5 and May 6, 2026.
Also being built nearby
All of 78205- 105 Auditorium Circle · At&t Services, Inc.Mar 22, 2024At&t 105 aud. elevator modernization — renovation/alteration — elevator room modifications
- 110 Lexington Ave · Trestle - Tlc El Tropicano, LPMay 20, 2024El tropicano hotel renovation — renovation/alteration — full interior remodel of an existing hotel that has been vacant since 2020 · 116 m away
- 300 Convent · 300 Convent, LLCOct 10, 2024Level 6 spec suite and common area — renovation/alteration — interior finish out for office · 140 m away
- 300 Convent St Level 21 And 22 · 300 Convent LLCAug 16, 2024Amegy bank san antonio — renovation/alteration — renovation of level 21 and level 22 office tenant suite space · 140 m away
- 500 Mccullough Avenue · City Public Energy ServiceDec 1, 2025Cps hq 11th floor new multipurpose room — renovation/alteration — enclose 750 sq ft of open office area with purchased modular walls to create multi-purpose space for staff · 258 m away
- 500 Mccullough Avenue · City Public Service EnergyMar 28, 2025Cps energy headquarters 9th flr finishout — new construction — interior office finish out of previous shell space including new restrooms, break broom conference rooms · 258 m away
- 100 Taylor Street · H5 100Oct 22, 2025H 2nd floor restroom renovation — renovation/alteration — renovation of existing restroom · 273 m away
- 112 E Pecan Street · Santa Clara Land Company, Ltd.Apr 6, 2026Pnc bank weston centre restroom renovation — renovation/alteration — restroom remodel of existing restrooms and addition of one unisex toilet room. total square footage approximately 410 sq ft · 357 m away
- 112 E Pecan · Santa Clara Land Company, LtdMar 27, 2024Kronkosky charitable foundation — renovation/alteration — interior remodel · 357 m away
- 112 E. Pecan St · Santa Clara Land Co LtdSep 24, 2026Visit san antonio — renovation/alteration — interior remodel of office space · 357 m away
- 711 Navarro Street · Tpp Epa, LLCAug 1, 2024Wiss, janney, elstner associates — renovation/alteration — interior renovation of office space · 363 m away
- 711 Navarro Street · Tpp Epa LLCFeb 2, 2026Kairoi residential office — renovation/alteration — renovation of a portion of the 6th floor of an existing office building into a new 7,680 sq ft office. portions of the existing floor will need to be demolished in preparation for new partitions, ceilings, finishes, mechanical, electrical and plumbing · 363 m away