New fencing and gates planned at Bob Hope Elementary

A project to demolish and replace existing fencing and gates and install new fencing and gates at Bob Hope Elementary was registered with TDLR on February 6, 2025. The registration lists Southwest ISD as the owner and shows the project as inspection complete.

Summarized from Texas Department of Licensing and Regulation records · updated Feb 6, 2025

Projects
1
1 filings
Latest filing
Feb 6, 2025
since Feb 6, 2025
Largest scope
200 sf
Estimated cost
$374K
state registration

Where this project stands

Inspected · closing out

SWISD FENCING PROJECT - BOB HOPE ELEMENTARY

200 sq ft · $374K est.

  1. RegisteredFeb 6, 2025
  2. Plan review
  3. ConstructionApr '25 – Dec '25
  4. Inspected
  5. Closednow

The building is substantially done. Move-in, fit-out and service work usually follow.

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. Demolish and replace existing fencing/gates and install new fencing/gates to secure campus. — bob hope elementary

    TDLR project registrationRenovation/AlterationInspection Complete200 sq ft$374K est.
    Tenant / owner
    Swisd Fencing Project - Bob Hope Elementary
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 3022 Reforma Dr, San Antonio, TX 78211

What is being built at 3022 Reforma Drive?

A fencing and gate replacement project is registered for Bob Hope Elementary at 3022 Reforma Drive. The work is intended to secure the campus.

When was the Bob Hope Elementary fencing project filed?

The TDLR project registration was filed on February 6, 2025. Its project number is TABS2025011300.

Is Southwest ISD replacing fencing at Bob Hope Elementary?

Yes. The TDLR registration describes demolishing and replacing existing fencing and gates, and installing new fencing and gates to secure the campus.

What is the estimated cost of the Bob Hope Elementary fencing project?

The TDLR registration lists an estimated project cost of $373,900. This is the applicant’s estimate for the project.

What is the status of the fencing project at Bob Hope Elementary?

The TDLR registration lists the project status as inspection complete.