Solar canopies registered at Southwest Service Center

A 660.30 kW DC solar system divided among three canopies is planned at the Southwest Service Center, 6927 W Commerce St. The project was registered with TDLR on March 26, 2024, as an addition to an existing building. The applicant’s estimated project cost is $1,440,434.

Summarized from Texas Department of Licensing and Regulation records · updated Mar 26, 2024

Projects
1
1 filings
Latest filing
Mar 26, 2024
since Mar 26, 2024
Largest scope
35,232 sf
Estimated cost
$1.4M
state registration

Where this project stands

In state plan review

Southwest Service Center

35,232 sq ft · $1.4M est.

  1. RegisteredMar 26, 2024
  2. Plan reviewnow
  3. ConstructionApr '24 – Apr '24
  4. Inspected
  5. Closed

Design is filed with the state. Subcontractors and suppliers are usually picked around now.

4 contacts on this project · 1 phone number

Permit & project history

1 project
  1. 660.30kw dc solar system divided among 3 canopies — southwest service center

    TDLR project registrationAdditions to Existing BuildingProject Registered35,232 sq ft$1.4M est.
    Tenant / owner
    Southwest Service Center
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 6927 W Commerce St

What is being built at 6927 W Commerce St?

A 660.30 kW DC solar system divided among three canopies is planned at the Southwest Service Center. TDLR registration TABS2024014681 was filed March 26, 2024.

Is the project at 6927 W Commerce St a solar installation?

Yes. The TDLR registration describes a solar system divided among three canopies at the Southwest Service Center.

When was the Southwest Service Center solar project registered?

It was registered with TDLR on March 26, 2024, under project number TABS2024014681.

How large is the solar system planned at the Southwest Service Center?

The registration lists a system capacity of 660.30 kW DC, divided among three canopies.

What is the estimated cost of the Southwest Service Center solar project?

The applicant’s TDLR estimate is $1,440,434 for the project.

What is being built near the City of San Antonio at 300 S. Callaghan?

A 660.30 kW DC solar system divided among three canopies was registered for the Southwest Service Center, about 303 meters from that landmark. The registration was filed March 26, 2024.