13200 Skyhawk Dr. San Antonio, TX 78249
San Antonio, TX 78249 · Northside ISD
Katherine Stinson Middle School plans a magnet addition
Northside ISD registered a project for a single-story 64,601-square-foot addition and a two-story, 31,187-square-foot renovation at Katherine Stinson Middle School. The Texas Department of Licensing and Regulation registration was filed January 7, 2025, with an estimated project cost of $12.7 million.
Summarized from Texas Department of Licensing and Regulation records · updated Jan 7, 2025
- Projects
- 1
- 1 filings
- Latest filing
- Jan 7, 2025
- since Jan 7, 2025
- Largest scope
- 31,187 sf
- Estimated cost
- $13M
- state registration
Where this project stands
Finishing up · inspection nextNew Magnet at Katherine Stinson MS
31,187 sq ft · $13M est.
- RegisteredJan 7, 2025
- Plan review
- ConstructionJun '25 – Aug '26
- Inspectednow
- Closed
Scheduled to finish Aug 7, 2026; the state inspection hasn't been filed yet.
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectSingle-story building addition: 64,601 sq ft and two-story building renovation: 31,187 sq ft — katherine stinson ms
TDLR project registrationRenovation/AlterationReview Complete31,187 sq ft$13M est.- Project #
- TABS2025008931
- Tenant / owner
- New Magnet At Katherine Stinson Ms
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 13200 Skyhawk Dr. San Antonio, TX 78249
What is being built at 13200 Skyhawk Drive in San Antonio?
The registration describes a single-story, 64,601-square-foot addition and a two-story, 31,187-square-foot renovation at Katherine Stinson Middle School for a new magnet program.
Is Katherine Stinson Middle School getting a new magnet program?
A TDLR project registration titled “New Magnet at Katherine Stinson MS” describes a building addition and renovation. It was filed January 7, 2025.
When was the Katherine Stinson Middle School project registered?
The Texas Department of Licensing and Regulation registration was filed January 7, 2025. Its status is listed as Review Complete.
How large is the addition at Katherine Stinson Middle School?
The registration describes a single-story addition of 64,601 square feet, along with a two-story renovation of 31,187 square feet.
How much will the Katherine Stinson Middle School project cost?
The applicant’s estimated cost for the project is $12.7 million, according to the TDLR registration.
Who is behind the project at Katherine Stinson Middle School?
The fact sheet identifies Northside ISD as the occupant or owner. The TDLR registration is for a new magnet project at the school.