5209 Leralynn St
Austin, TX 78751
5209 Leralynn St: 1 project on record
City of Austin lists 1 filing across 1 project at 5209 Leralynn St, Austin, TX 78751. The most recent, filed October 23, 2024, covers: “Total demolition of detached garage 432 sq ft circa 1949”.
Compiled from City of Austin records · updated Oct 23, 2024
- Projects
- 1
- 1 filings
- Latest filing
- Oct 23, 2024
- since Oct 23, 2024
- Largest scope
- —
- Listed value
- —
Where this project stands
FinaledTotal demolition of detached garage 432 sq ft circa 1949
- AppliedOct 8, 2024
- IssuedOct 23, 2024
- WorkOct '24 – Aug '25
- Final inspectionAug 6, 2025
Passed final inspection Aug 6, 2025.
2 contacts on this project · 2 phone numbers
Permit & project history
1 projectTotal demolition of detached garage 432 sq ft circa 1949
Total demolition of detached garage 432 sq ft circa 1949
City of Austin permitBuilding PermitFinal- Record
- 2024-138873 BP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 5209 Leralynn St
What is being built at 5209 Leralynn St?
The latest filing (City of Austin permit 2024-138873 BP, October 23, 2024) covers total demolition of detached garage 432 sq ft circa 1949.
How many permits and filings does 5209 Leralynn St have?
1 filing across 1 project, from October 23, 2024 to October 23, 2024.
Is there other construction near 5209 Leralynn St?
Yes. Nearby filings include 5207 Leralynn St (demolition and dispose of existing electrical panel and meter, May 11, 2026); 5211 Leralynn St (cast iron replacement remove and replacing cast iron piping from under the floor near the kitchen sink and under bathroom 1. dig an opening in the yard where the cleanout is and uncover the cast iron pipe. dig 3-4 feet under the house following where the cast iron line is buried. homeowner will open wall in the closet behind bathroom 1 and we will put two 2x4s and an anchor to secure the new 4 cast iron vent we will install in the closet wall. we will repipe bathroom 1 under the house which includes flashing for the toilet and a new p-trap for the bathtub and probably new overflow and drain to the bathtub, Aug 5, 2025); 5203 Leralynn St (construct new like for like driveway approach of 12 ft, Jan 23, 2025).
How do I get alerts for new permits at 5209 Leralynn St?
Watch this address on groundranger and you'll get an email when a new permit or project filing appears here or nearby.
Also being built nearby
All of 78751- 5207 Leralynn StMay 11, 2026Demolition and dispose of existing electrical panel and meter · 16 m away
- 5211 Leralynn StAug 5, 2025Cast iron replacement remove and replacing cast iron piping from under the floor near the kitchen sink and under bathroom 1. dig an opening in the yard where the cleanout is and uncover the cast iron pipe. dig 3-4 feet under the house following where the cast iron line is buried. homeowner will open wall in the closet behind bathroom 1 and we will put two 2x4s and an anchor to secure the new 4 cast iron vent we will install in the closet wall. we will repipe bathroom 1 under the house which includes flashing for the toilet and a new p-trap for the bathtub and probably new overflow and drain to the bathtub · 18 m away
- 5203 Leralynn StJan 23, 2025Construct new like for like driveway approach of 12 ft · 49 m away
- 304 Genard StMar 5, 2025Level 2 ev charger powered by a 60amp circuit breaker. run #6 thhn c.u. & #10 thhn c.u. ground through <40 feet new flex conduit and <5 feet new 3/4 emt conduit to power the level 2 ev charger at 48amp constant draw · 80 m away
- 303 W North Loop BlvdMar 18, 2024Replacement of complete existing central heat and air system with or without duct work · 103 m away
- 406 Genard StFeb 2, 2024Pulled gas meter. replace gas service · 136 m away
- 212 W North Loop BlvdFeb 21, 2025Amnesty co · 139 m away
- 405 W North Loop BlvdJan 19, 2024Install tankless gas water heater · 144 m away
- 214 W 51st StNov 27, 2023Replace sewer pipe below slab via tunel for unit b · 144 m away
- 310 W North Loop BlvdMay 10, 2024Construct new driveway approach of 12 ft. no sidewalk inspection per plan review · 150 m away
- 409 W North Loop BlvdJun 30, 202550ft sewer line · 170 m away
- 500 Zennia StMar 17, 2024Ev install · 172 m away
More demolitions in 78751.