42,000-square-foot slab planned for broadcast infrastructure
A 42,000-square-foot slab is planned next to and accessed from the existing convention center dock at 1225 Canton St. A Dallas commercial new-construction permit filed August 19, 2025, describes grading and retaining walls and says the slab is intended to support temporary broadcast infrastructure for FIFA 2026. A December 10, 2025, electrical permit covers switches and transformers for the new slab.
Summarized from City of Dallas records · updated Dec 10, 2025
- Projects
- 2
- 2 filings
- Latest filing
- Dec 10, 2025
- since Aug 19, 2025
- Largest scope
- —
- Listed value
- —
Permit & project history
2 projectsProvide (2) 480v switches, (2) 1500kw transformers, and (2) 15kv switches at vault eprovide (2) 480/277v switches, (2) 1500kw transformers, and (2) 15kv switches at new slab
Provide (2) 480v switches, (2) 1500kw transformers, and (2) 15kv switches at vault eprovide (2) 480/277v switches, (2) 1500kw transformers, and (2) 15kv switches at new slab
City of Dallas permitCommercial Electrical PermitThe project consists of a 42,000 sq ft slab adjacent to and accessed from the existing convention center dock. the slab is working with grading and retaining walls and is essentially flat, just one level. electrical equipment for power service is intended to power temporary use and installation of broadcast infrastructure for fifa 2026, which will be specified in a separate permit
The project consists of a 42,000 sq ft slab adjacent to and accessed from the existing convention center dock. the slab is working with grading and retaining walls and is essentially flat, just one level. electrical equipment for power service is intended to power temporary use and installation of broadcast infrastructure for fifa 2026, which will be specified in a separate permit
City of Dallas permitCommercial New Construction Permit
Sources: City of Dallas
Questions about 1225 Canton St
What is being built at 1225 Canton St in Dallas?
A City of Dallas permit describes a 42,000-square-foot slab next to the existing convention center dock. It includes grading and retaining walls.
What will the slab at 1225 Canton St be used for?
The August 19, 2025, permit says power service is intended for temporary use and installation of broadcast infrastructure for FIFA 2026. The broadcast infrastructure is to be specified in a separate permit.
How large is the new slab at 1225 Canton St?
The new-construction permit describes a 42,000-square-foot slab.
When was the project at 1225 Canton St permitted?
The new-construction permit, COM-NEW-25-000135, was filed August 19, 2025. An electrical permit, COM-ELC-25-003555, was filed December 10, 2025.
What electrical work is planned at 1225 Canton St?
Permit COM-ELC-25-003555 describes two 480-volt switches, two 1,500-kilowatt transformers, and two 15-kilovolt switches for the new slab.
Is the slab at 1225 Canton St near the FIFA International Broadcasting Center?
The FIFA International Broadcasting Center at 650 S Griffin St is listed as a nearby landmark, about 312 meters away. The 1225 Canton St permit says the slab is intended to support temporary broadcast infrastructure for FIFA 2026.
Also being built nearby
All of 75202- 706 N Griffin StSep 30, 2026Demolish building. haul off debris. no trees · 256 m away
- 650 S Griffin St · City Of DallasNov 12, 2026Evolve concepts has been contracted by hyrox to install and subsequently remove three temporary, freestanding modular structures inside the kay bailey hutchinson convention center at 650 s griffin st, dallas, tx 75202 for a hyrox athletic competition. the installation consist of two elevated spectator viewing platforms and one elevated pedestrian course bridge. the structures will be assembled using engineered modular components, with stairs, guardrails and supporting structural elements as detailed in the submitted drawings. all structures are temporary, will be removed following the event, and will not involve permanent modifications to the existing building · 312 m away
- 1011 S Akard StAug 14, 2026Rpz backflow device instillation · 330 m away
- 1301 Young StJul 25, 2025Manual recreation***2403041139 · 352 m away
- 1500 Marilla St · City Of DallasSep 10, 2026Protest event stage: september 10, 2026 5pm-9pmset up stage to start by noon - ready for inspection at 4pm, start program at 5pm. expecting 5-7,500 attendees, open to the public and at no cost to enter. the event is soon its 4th year and hosts a small procession leading up to the grito at 7pm, starts at 6pm. stage is 16x24x3 - side rails and two sets of stage, so sections are in 4x4 ft so thats with 16 = 4 panes (4x4 = 16) and length is = 6 panels (4x6 = 24). so 4 down and 6 panels across. key specifications of artfox easy stage• dimensions: 4x4 ft per standard platform section.• height adjustment: infinitely adjustable from 2 feet to 3.6 feet (60–110 cm).• design features: built with a fast-lock/unlock mechanism, attached folding legs, micro-adjustment rubber leveling feet, and safety pins.• durability: sturdy aluminum concert truss construction designed to support high weight capacity and active use like jumping or dancing.• artfox manufactures the portable easy stage system, which features an adjustable, heavy-duty modular design1500 marilla st dallas, tx 75201• https://www.artfox.net/truss-d0301008.htmlstage dimensions: 24ft x 16ft3ft high4ft high back railing2 4x8ft speaker wings attached to left and right side of stage. aluminum stairs stage left top view: 4ft back railing24ft 3ft high front view 4x8 ft · 385 m away
- 1500 Marilla StNov 17, 2026Dallas marathon 2026. staging and event trussing start line, and 2x truss walkway bridge · 385 m away
- 1500 Marilla Street · City Of DallasJul 28, 2025Dallas city hall level l1 restroom renovation — renovation/alteration — renovations to approximately 500 square feet of restroom space to ensure compliance with texas accessibility standards (tas) · 385 m away
- 1100 Peters StDec 15, 2020Install lawn sprinkler · 393 m away
- 971 S Lamar StOct 30, 2020Interior remodel only · 400 m away
- 1413 Griffin St WApr 23, 2026New driveway and approach · 420 m away
- 1100 S Akard StDec 9, 2020Gas test · 426 m away
- 1111 S Akard StMar 31, 2026Unit 304!!!!!!water heater · 430 m away