Entry and garage alterations, plus electrical repairs, at 7550 N Central Expy
Permits indicate work to the existing commercial building at 7550 N Central Expy, including steel framing over the entry and garage bays, new siding and a stucco cornice. The alteration permit was filed April 1, 2026; a separate electrical permit filed October 15, 2026, covers repairs to electrical boxes and branch circuits.
Summarized from City of Dallas records · updated Oct 15, 2026
- Projects
- 2
- 2 filings
- Latest filing
- Oct 15, 2026
- since Apr 1, 2026
- Largest scope
- —
- Listed value
- —
Permit & project history
2 projectsCorrect existing electrical boxes and branch circuits by repairing connections, securing wiring and connectors, replacing missing covers, and addressing visible hazards to meet code
Correct existing electrical boxes and branch circuits by repairing connections, securing wiring and connectors, replacing missing covers, and addressing visible hazards to meet code
City of Dallas permitCommercial Electrical PermitMcr install steel stud framing over entry area and garage bays, attached to existing structure. install plywood sheathing and metal panel siding. install stucco cornice above. paint remainder of building
Mcr install steel stud framing over entry area and garage bays, attached to existing structure. install plywood sheathing and metal panel siding. install stucco cornice above. paint remainder of building
City of Dallas permitCommercial Alteration Addition Permit
Sources: City of Dallas
Questions about 7550 N Central Expy
What is being built at 7550 N Central Expy in Dallas?
A City of Dallas alteration permit describes steel stud framing over the entry and garage bays, plywood sheathing, metal panel siding and a stucco cornice on the existing structure. A separate permit covers electrical repairs.
When were permits filed for work at 7550 N Central Expy?
The alteration permit, COM-ALT-ADD-26-000561, was filed April 1, 2026. The electrical permit, COM-ELC-26-005139, was filed October 15, 2026.
What work does the April 2026 permit cover at 7550 N Central Expy?
Permit COM-ALT-ADD-26-000561 describes framing over the entry and garage bays, installing plywood sheathing and metal panel siding, adding a stucco cornice and painting the rest of the building.
What does the electrical permit cover at 7550 N Central Expy?
Permit COM-ELC-26-005139 describes correcting existing electrical boxes and branch circuits, including repairing connections, securing wiring and connectors, replacing missing covers and addressing visible hazards to meet code.
Is a new building going up at 7550 N Central Expy?
The April 2026 permit describes alterations attached to an existing structure. The listed records do not describe construction of a new building.
What business is at 7550 N Central Expy?
The permit records do not identify a business or tenant for the address.
Also being built nearby
All of 75206- 7909 Stanford AveMay 15, 2025In ground pool and spa · 99 m away
- 5409 Greenville Ave · Greenville Ave Investment, LLCJan 16, 2025Alchemy wellness — renovation/alteration — 3120 sq ft of interior walls and doors, hvac, electrical and lighting, plumbing and 2 ada restrooms, ceiling tiles and grid · 146 m away
- 5500 Greenville Ave · Wpf Operating LLCOct 28, 2026Clean and show for meter release. the suite is vacant · 181 m away
- 5315 Greenville AveDec 9, 2025Gas pressure test per atmos since unit was vacant for over 60 days · 184 m away
- 7906 Purdue StNov 4, 2026Application for fence permit · 187 m away
- 7908 Hanover AveAug 7, 2026Roof replace with iko dynasty drift shack class 4 shingle, synthetic felt, metal type of pipe boots and vents · 189 m away
- 7831 Amherst AveAug 27, 2025Two 40 gallon gas water heaters · 193 m away
- 7902 Stanford AveOct 19, 2020Install lawn sprinkler · 196 m away
- 5521 Greenville AveJul 6, 2026Floor drain in restroom · 213 m away
- 5302 Greenville AveMar 6, 2026Install (1) 10 row x 24' non-elevated bleacher and (1) 10 row x 36' non-elevated bleacher in parking lot for upcoming st. patrick's day parade. install will be on march 13th and dismantle will be on march 14, 2026. bleachers are modular style temporary bleachers designed specifically for special events · 214 m away
- 7902 Amherst AveAug 20, 20263 ton deluxe straight cool coil and condenser only – horizontal · 221 m away
- 7828 Hanover AveApr 14, 2026Replace 4.0 ton system with a 4.0 ton system for the first floor · 223 m away