9301 Forest Lane
Dallas, TX 75243 · Walmart Stores Texas LLC
Walmart refrigeration upgrade planned on Forest Lane
A refrigeration system upgrade is planned at the Walmart at 9301 Forest Lane, including replacement cases or evaporator coils and a refrigeration skid on the roof. The project was registered with TDLR on February 25, 2025, for 58,243 square feet; the applicant estimated its cost at $1.5 million.
Summarized from Texas Department of Licensing and Regulation records · updated Feb 25, 2025
- Projects
- 1
- 1 filings
- Latest filing
- Feb 25, 2025
- since Feb 25, 2025
- Largest scope
- 58,243 sf
- Estimated cost
- $1.5M
- state registration
Where this project stands
Finishing up · inspection next2427-1006 Walmart CAPX-Refr
58,243 sq ft · $1.5M est.
- RegisteredFeb 25, 2025
- Plan review
- ConstructionJul '25 – Nov '25
- Inspectednow
- Closed
Scheduled to finish Nov 4, 2025; the state inspection hasn't been filed yet.
4 contacts on this project · 2 phone numbers
Permit & project history
1 projectReplace existing cases or evap coils with alternative glycol or co2 cases or evaps. a glycol or co2 refrigeration skid will be placed on the roof. (58,243sf) — walmart 2427-1006
TDLR project registrationRenovation/AlterationReview Complete58,243 sq ft$1.5M est.- Project #
- TABS2025012679
- Tenant / owner
- 2427-1006 Walmart Capx-Refr
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 9301 Forest Lane
What is being built at 9301 Forest Lane?
A TDLR-registered renovation would replace existing refrigeration cases or evaporator coils with glycol or CO2 alternatives and place a refrigeration skid on the roof. The registration describes work across 58,243 square feet.
Is a new Walmart being built on Forest Lane?
The February 25, 2025 TDLR registration describes a renovation to an existing Walmart, not a new store. The work covers refrigeration equipment.
When was the Walmart refrigeration project permitted?
The project was registered with TDLR on February 25, 2025. Its registration number is TABS2025012679.
How much will the Walmart project at 9301 Forest Lane cost?
The applicant estimated the project cost at $1.5 million in the TDLR registration. This is an estimate, not a confirmed final project cost.
What's changing at Walmart near Kyli Restaurant on Forest Lane?
The Walmart at 9301 Forest Lane has a registered refrigeration upgrade: existing cases or evaporator coils would be replaced with glycol or CO2 alternatives, and a refrigeration skid would be placed on the roof. TDLR recorded the project on February 25, 2025.
What's being renovated at Walmart near Bank of America on Forest Lane?
A refrigeration-system renovation is registered at the Walmart at 9301 Forest Lane, about 177 meters from the Bank of America listed in the records. The project registration calls for replacement cases or evaporator coils and a roof-mounted refrigeration skid.
Also being built nearby
All of 75243- 9301 Forest Ln · Walmart Stores Texas LLCOct 22, 2026Mcr install new interior door in breakroom.install new interior and exterior doors in return storage
- 9254 Forest LnJul 2, 2026Hvac replacement lennox 2.5 ton straight electric upflowel16 · 86 m away
- 11836 Judd CtFeb 4, 2026Perform gas pressure test so that atmos can install new gas meter · 170 m away
- 11817 Judd CtAug 4, 2026Expanding suite #111 for retail shop · 172 m away
- 9308 Forest Ln · Bank Of AmericaSep 4, 2026Scope of work is an exterior renovation / maintenance project. scope includes site work and exterior building maintenance. site work includes: repair and restripe concrete pavement, including ada markings, to match existing; clean site lights and concrete bases throughout; remove bollards and concrete islands associated with drive-through canopy and section of depressed concrete paving around drive-through canopy; remove concrete paving to be replaced; clean, patch, and repair all concrete sidewalks, pavement, curbs, and pads throughout; repaint caution curbs throughout to match existing; paint curb of remote concrete island with yellow caution paint; install two (2) new bollards with bac standard bollard covers and hc signage; provide new bac standard bollard covers to existing bollards; clean and paint ada railing; remove and replace portion of planter wall in r.o.w.; refresh landscaping, including planting, pruning, and mulch.exterior building maintenance includes: clean, patch, and paint building facades; paint all conduit, wall-mounted utilities, downspouts, and scuppers to match adjacent finishes; remove and replace can light fixtures at window and entry soffits with new bac standard led recessed can light fixtures; clean entrance canopy skylights and replace cracked skylights if conditionwarrants; clean and paint entrance canopy. general contractor to evaluate condition of wall , where drive-through canopy is removed, notify architect of any deficiencies prior to proceeding with wall closure ; repair and repoint brick exterior wall around, and behind, drive-through canopy where canopy and vac tubes panel is removed to ensure enclosure.all signage under separate permit (n.i.c.) all signage shown is for reference only. general contractor to coordinate their work with bank of america sign vendor work · 177 m away
- 9184 Forest LnMar 10, 2026Replacing panel and pulling in home runs · 177 m away
- 9180 Forest LnApr 30, 2026Install 28 total pilingsthis is for building 19 · 179 m away
- 9310 Forest Lane · Kyli RestaurantMay 18, 2026Kyli restaurant — new construction — interior remodel of a new restaurant · 180 m away
- 9310 Forest LnOct 5, 2026Commercial remodeling · 180 m away
- 11837 Judd CtJul 15, 2026Clean and show only. vacant suite · 182 m away
- 9170 Forest LnNov 10, 2026Replace existing electrical panel · 182 m away
- 11857 Judd CtJun 29, 2026Refreshment area installation with countertop, cabinets, fridge, sink, coffee machine, and microwave. additional restrooms, one for female, and one for male. exposed plumbing if allowed. wall-hung toilets. please advise if floor drain is required · 198 m away