Concrete driveway and approach replacement permitted
A concrete driveway and approach replacement was permitted at 7811 Glenneagle Dr on April 20, 2026. The work includes removing and hauling away the existing concrete, regrading, and installing a new concrete surface.
Summarized from City of Dallas records · updated Apr 20, 2026
- Projects
- 1
- 1 filings
- Latest filing
- Apr 20, 2026
- since Apr 20, 2026
- Largest scope
- —
- Listed value
- —
Permit & project history
1 projectDriveway and approach will be both removed and replaced with new concrete we will be braking apart and hauling away concrete to a dump site " big city crushed concrete" we will also be regrading and making sure all grade is how its supposed to be as plans and all rebar is to specs and placed properly before pouring as well as forms making sure all forms are set to proper elevation also we will adding proper base rock for base and making sure its properly compacted
Driveway and approach will be both removed and replaced with new concrete we will be braking apart and hauling away concrete to a dump site " big city crushed concrete" we will also be regrading and making sure all grade is how its supposed to be as plans and all rebar is to specs and placed properly before pouring as well as forms making sure all forms are set to proper elevation also we will adding proper base rock for base and making sure its properly compacted
City of Dallas permitResidential Drive Approach and Sidewalk Permit
Sources: City of Dallas
Questions about 7811 Glenneagle Dr
What work is permitted at 7811 Glenneagle Dr?
A City of Dallas permit covers removing and replacing the driveway and approach with new concrete. The permit also describes regrading and preparing the base and forms.
When was the driveway replacement permitted at 7811 Glenneagle Dr?
The permit was filed on April 20, 2026. Its number is RES-DSW-26-000204.
Is a new home being built at 7811 Glenneagle Dr?
The available permit record is for residential driveway and approach work, not a new home.
Will the existing concrete be removed at 7811 Glenneagle Dr?
Yes. The permit description says the existing driveway and approach concrete will be broken apart and hauled away before replacement.
What preparation is included in the Glenneagle Drive permit?
The description includes regrading, adding and compacting base rock, and setting forms and rebar before pouring the concrete.
Also being built nearby
All of 75248- 7812 Glenneagle DrSep 17, 2026Installing 8 total piers · 15 m away
- 7807 Glenneagle DrApr 1, 2026Gas test for meter release · 17 m away
- 7815 Glenneagle DrFeb 6, 2026Sewer repair · 17 m away
- 7804 Glenneagle DrJun 1, 2026Sewer replacement via trench and tunnel including the laundry riser · 29 m away
- 7802 Glenneagle DrDec 31, 2025Replace 2 gas tank water heater · 37 m away
- 7826 Glenneagle DrFeb 20, 2026X2 50 gal gas water heaters right side hall · 70 m away
- 7703 Applecross LnMay 21, 2026Repair sewer by tunnel · 76 m away
- 7701 Kilbride CirJul 22, 2026Under slab sewer repipe · 99 m away
- 16212 Spring Creek RdJul 22, 2026-demolish and remove approximately 35 linear feet (lf) of existing city curb to install a new residential driveway approach.-demolish and remove approximately 5' x 35' of existing city sidewalk and reconstruct it as part of the new driveway approach in accordance with city of dallas standards.-demolish and replace the existing front residential concrete walkway, approximately 5' x 31', matching the new concrete improvements.-construct a new reinforced concrete driveway, approximately 30' x 25', aligned with the new curb cut and driveway approach.-the front yard is approximately 3,100 square feet,there is a tree there but it will not be touched at all. everything that is modified is 5feet or more away · 105 m away
- 16210 Spring Creek RdAug 26, 2026Install 25 piers · 106 m away
- 7702 Kilbride CirApr 13, 2026Foundation repair-install 15 piers · 109 m away
- 7704 Kilbride CirJul 20, 2026Sewer repipe · 110 m away