groundranger
Recent · latest filing Jun 2025Commercial

2330 N International Parkway

Dfw Airport, TX 75261 · Dfw Terminal C - Phase 2, Dfw Terminal C - Phase 3 + 6 more

DFW Terminal C renovation spans multiple phases

DFW Terminal C, a multi-tenant airport terminal, is undergoing phased renovations that include replacing concourse areas and renovating lower levels. TDLR registrations for work in the northern and central thirds of the terminal were filed June 27, 2025; Phase 1A registrations were filed in February 2024.

Summarized from Texas Department of Licensing and Regulation records · updated Jun 27, 2025

Projects
11
11 filings
Latest filing
Jun 27, 2025
since Feb 19, 2024
Largest scope
540,000 sf
Estimated cost
$503M
state registration

Where this project stands

Under construction

DFW Terminal C - Phase 2

383,980 sq ft · $503M est.

  1. RegisteredJun 27, 2025
  2. Plan review
  3. ConstructionJun '26 – Sep '28
  4. Inspected
  5. Closed
20% through of a 28-month buildJun 1, 2026 → Sep 30, 2028

4 contacts on this project · 3 phone numbers

Permit & project history

11 projects
  1. Replacement of concourse level and renovations of lower level – northern third of terminal c — dallas fort worth international airport terminal c

    TDLR project registrationRenovation/AlterationReview Complete383,980 sq ft$503M est.
    Tenant / owner
    Dfw Terminal C - Phase 2
    Design firm
    Pro
    Contact
    Pro
  2. Replacement of concourse level and renovations of lower level - central third of terminal c — dallas fort worth international airport terminal c

    TDLR project registrationRenovation/AlterationReview Complete353,033 sq ft$412M est.
    Tenant / owner
    Dfw Terminal C - Phase 3
    Design firm
    Pro
    Contact
    Pro
  3. This work scope includes the addition of a passenger access corridor to move patrons beyond the construction area and minimize the impact to airport operations. — dallas fort worth international airport

    TDLR project registrationRenovation/AlterationProject Closed540,000 sq ft$11M est.
    Tenant / owner
    Pro
    Design firm
    Pro
    Contact
    Pro
  4. The renovation of this area in terminal c includes, civil, architectural, structural, fire protection, mep, and communications of the core and shell of the ramp, concourse and third levels. — dallas fort worth international airport

    TDLR project registrationRenovation/AlterationReview Complete540,000 sq ft$332M est.
    Tenant / owner
    Dfw Central Terminal Area Expansion Terminal C - Phase 1a
    Design firm
    Pro
    Contact
    Pro
  5. This scope includes civil and telecom work to create a construction access gate at the south end of terminal c by running electricity/communications to a manned security gate w an electronically controlled arm. — dallas fort worth international airport

    TDLR project registrationRenovation/AlterationProject Closed9,687 sq ft$5.0M est.
    Tenant / owner
    Dfw Ctae -Terminal C - Phase 1a - Construction Entrance Gate
    Design firm
    Pro
    Contact
    Pro
  6. DFW C11 Gate Area

    The scope of this work includes the renovation to the existing security checkpoint at gate c11, with architectural, mechanical, electrical, fire protection/alarm and communications systems. — dallas fort worth international airport

    TDLR project registrationRenovation/AlterationProject Closed5,922 sq ft$2.0M est.
    Tenant / owner
    Dfw C11 Gate Area
    Design firm
    Pro
    Contact
    Pro
  7. Package c5 - pier c passenger boarding bridge equipment: project includes the passenger boarding bridge equipment and fixed bridges to serve the new pier c gates. — dallas fort worth international airport, terminal c

    TDLR project registrationNew ConstructionReview Complete15,193 sq ft$12M est.
    Tenant / owner
    Central Terminal Area Renovation Terminals C And A - Package C5
    Design firm
    Pro
    Contact
    Pro
  8. Project consists of the renovation of existing spaces to function as temporary boarding area & gate lounges for gates c26 & c27.additionally, this project will relocate the existing aa a rebooking center to a new location. — dallas fort worth international airport, terminal c

    TDLR project registrationRenovation/AlterationProject Closed11,552 sq ft$1.2M est.
    Tenant / owner
    Central Terminal Area Renovation Terminals C And A - Package C2
    Design firm
    Pro
    Contact
    Pro
  9. Package c2 - terminal c renovation - enabling gates c26 and c27, and rebooking center relocation: project consists of the renovation of existing spaces to function as temporary boarding area and gate lounges for gates c26 and c27. additionally, this — dfw, terminal c

    TDLR project registrationRenovation/AlterationProject Closed11,552 sq ft$1.2M est.
    Tenant / owner
    Central Terminal Area Renovation Terminals C And A - Package C2
    Design firm
    Pro
    Contact
    Pro
  10. Package c5 - pier c passenger boarding bridge equipment: project includes the passenger boarding bridge equipment and fixed bridges to serve the new pier c gates. — dfw airport, terminal c

    TDLR project registrationNew ConstructionProject Closed15,193 sq ft$12M est.
    Tenant / owner
    Central Terminal Area Renovation Terminals C And A - Package C5
    Design firm
    Pro
    Contact
    Pro
  11. Package c4 - pier c building - core, shell and interiors: project consists of new construction to add a pier on the south skylink side of the terminal providing a total of 10 gates (6 new gates, plus 4 existing gates to be reconfigured) — dallas fort worth international airport, terminal c

    TDLR project registrationNew ConstructionInspection Complete139,453 sq ft$104M est.
    Tenant / owner
    Central Terminal Area Renovation Terminals C And A - Package C4
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 2330 N International Parkway

What is being renovated at 2330 N International Parkway?

DFW Terminal C is undergoing phased renovations. The latest registrations describe concourse replacement and lower-level renovations in the terminal’s northern and central thirds.

When were the latest Terminal C renovation projects filed?

The registrations for Terminal C Phases 2 and 3 were filed June 27, 2025. They are listed as TABS2025022276 and TABS2025022272.

What work is included in Terminal C Phase 1A?

The Phase 1A registration describes civil, architectural, structural, fire protection, mechanical, electrical and communications work to the ramp, concourse and third-level core and shell. It was filed February 20, 2024, as TABS2024012026.

How much of Terminal C is covered by Phases 2 and 3?

The TDLR registrations list 383,980 square feet for Phase 2 in the northern third and 353,033 square feet for Phase 3 in the central third.

Is the work at DFW Terminal C a new building?

The registrations describe renovations and alterations to the existing terminal, including concourse replacement and lower-level work.

What's being renovated near DFW Terminal D?

TDLR records show phased renovation work at DFW Terminal C, about 360 meters from Terminal D. The work includes concourse replacement and lower-level renovations.

Also being built nearby

All of 75261

More cell towers & telecom in 75261.

Email me when it passes inspection