2330 North International Parkway
Dfw Airport, TX 75261 · Dfw High C Restroom Fixture Replacement, American Airlines Back Of House Restrooms + 4 more
DFW Terminal C plans a six-level garage and two garage renovations
TDLR registrations show plans for a new six-level parking garage at Terminal C’s existing Garage C location, along with renovations to Garages A and B. Those three projects were registered October 12, 2023; later registrations cover employee restroom renovations in 2024 and public restroom fixture replacements in 2025.
Summarized from Texas Department of Licensing and Regulation records · updated Apr 28, 2025
- Projects
- 6
- 6 filings
- Latest filing
- Apr 28, 2025
- since May 14, 2024
- Largest scope
- 5,000 sf
- Estimated cost
- $111M
- state registration
Where this project stands
In state plan reviewDFW High C Restroom Fixture Replacement
190 sq ft · $608K est.
- RegisteredApr 28, 2025
- Plan reviewnow
- ConstructionMay '25 – Jun '25
- Inspected
- Closed
Design is filed with the state. Subcontractors and suppliers are usually picked around now.
4 contacts on this project · 3 phone numbers
Permit & project history
6 projectsReplace existing lavatory fixtures in public restrooms with new fixtures. (190sf) — dfw airport
TDLR project registrationRenovation/AlterationProject Registered190 sq ft$608K est.- Project #
- TABS2025017620
- Tenant / owner
- Dfw High C Restroom Fixture Replacement
- Design firm
- Pro
- Contact
- Pro
Renovation of 13 ramp level employee restrooms — terminal c
TDLR project registrationRenovation/AlterationReview Complete5,000 sq ft$1.3M est.- Project #
- TABS2024018530
- Tenant / owner
- American Airlines Back Of House Restrooms
- Design firm
- Pro
- Contact
- Pro
Renovation of garage b at terminal c — dfw airport
TDLR project registrationRenovation/AlterationReview Complete656,992 sq ft$24M est.- Project #
- TABS2024003006
- Tenant / owner
- Dfw Terminal C Garage And Roadways Package 3
- Design firm
- Pro
- Contact
- Pro
Renovation of parking garage a at terminal c — dfw airport
TDLR project registrationRenovation/AlterationReview Complete650,351 sq ft$25M est.- Project #
- TABS2024003004
- Tenant / owner
- Dfw Terminal C Garage And Roadways Package 2
- Design firm
- Pro
- Contact
- Pro
New construction of a 6 level parking garage at the existing garage c location at terminal c — dfw airport
TDLR project registrationNew ConstructionReview Complete802,707 sq ft$111M est.- Project #
- TABS2024003000
- Tenant / owner
- Dfw Terminal C Garage And Roadways Package 1
- Design firm
- Pro
- Contact
- Pro
Interior renovation — dallas/fort worth international airport
TDLR project registrationRenovation/AlterationProject Closed1,422 sq ft$1.0M est.- Project #
- TABS2023016904
- Tenant / owner
- Ampersand Dfw
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 2330 North International Parkway
What is being built at 2330 North International Parkway?
TDLR records describe a new six-level parking garage at DFW Terminal C’s existing Garage C location, plus renovations to Garages A and B. The garage projects were registered October 12, 2023.
What is happening at DFW Terminal C?
The registered work includes a new six-level garage, renovations to two existing garages, and restroom work. The garage projects were registered in October 2023, and restroom projects were registered in May 2024 and April 2025.
Is DFW building a new parking garage at Terminal C?
A TDLR registration describes new construction of a six-level garage at the existing Garage C location. The project, TABS2024003000, was registered October 12, 2023.
Are the existing Terminal C garages being renovated?
TDLR records describe renovations to Parking Garage A and Garage B. Both projects were registered October 12, 2023: TABS2024003004 for Garage A and TABS2024003006 for Garage B.
Are the restrooms at Terminal C being renovated?
Records describe renovation of 13 ramp-level employee restrooms in a project registered May 14, 2024, and replacement of public restroom lavatory fixtures in a project registered April 28, 2025. The registrations are TABS2024018530 and TABS2025017620.
Is this project for one tenant?
The records cover multiple projects at DFW Airport, including parking garage and restroom work at Terminal C. They do not describe the address as a single-tenant project.
Also being built nearby
All of 75261- 2330 N International Parkway · Dallas Fort Worth International Airport Terminal CJun 27, 2025Dfw terminal c - phase 2 — renovation/alteration — replacement of concourse level and renovations of lower level – northern third of terminal c
- 2330 N International Pkwy · City Of Dallas/Dfw Airport DivisionAug 26, 2026Dfw - tc terminal c - south skylink exterior escalator and canopy — additions to existing building — reconfiguration of existing space to accommodate new tenants. total scope includes storage. total area: approximately 2,206 sq ft
- 2330 N International Parkway, Dfw Airport Terminal A, Space: A-2-040j-A01 · Dfw AirportApr 29, 2026Gate escape dfw — new construction — tenant fit-out of new concessions space within terminal a of dfw airport
- 2330 N International Parkway · Dallas City OfApr 1, 2024Dfw ctae - package 5 - north sort pier addition — renovation/alteration — the scope of this work includes the construction of two canopies to cover two baggage handling conveyor belts
- 2330 North International Parkway Terminal A Gate 21 · Dfw International AirportJul 30, 2025Auntie anne's pretzels — renovation/alteration — new finishes, new millwork, new equipment
- 2330 North International Parkway Terminal B Gate 22 B-2-069c-A01 · Dfw International Airport Terminal BMay 13, 2025Tgif on the fly — renovation/alteration — concessions tenant improvements including partition wall, electrical and data outlets, millwork installation
- 2330 North International Parkway Terminal C C-2-106e-A01 · Dfw International Airport Terminal CNov 20, 2024Ampersand kiosk — renovation/alteration — installation of new prefabricated kiosk with limited millwork addition and attendant electrical and plumbing infrastructure
- 2330 N International Pkwy · City Of Dallas/Dfw Airport DivisionNov 20, 2025Dfw - tc ph. 2.1/2.2 enabling package - dfw custodial & shared break room — renovation/alteration — reconfiguration of existing space to accommodate new tenants. total scope includes storage and an office. total area: approximately 1,090 sq ft
- 2333 S. International Pkwy, Terminal D · Dfw Airport - Terminal DOct 30, 2024One-stop security: aa breakroom — renovation/alteration — renovation of storage room into a breakroom space for employees only. (1,250 s.f. total) · 360 m away
- 2333 S. International Pkwy. Space D-Nv114Jun 10, 2025Inmotion — renovation/alteration — interior build-out of existing mercantile concession space (668 sq ft) at dfw terminal d on level 3 to a new mercantile concession space within the same footprint · 360 m away
- 2333 S. International Pkwy, Space Number D-Sc103Jun 10, 2025Dude, sweet chocolate — renovation/alteration — interior build-out of existing mercantile concession space (337 sq ft) at dfw terminal d on level 3 to a new mercantile concession space within the same footprint · 360 m away
- 2333 South International Parkway Dfw Airport 75261 · Dfw AirportFeb 18, 2025Dfw airport terminal d - chili's — renovation/alteration — existing shell space finish-out for new concessions venue at airport terminal. the total square footage is 5434 · 360 m away