7909 Izetta Ln
Austin, TX 78744
7909 Izetta Ln: 2 projects on record
City of Austin lists 2 filings across 2 projects at 7909 Izetta Ln, Austin, TX 78744. The most recent, filed September 20, 2024, covers: “Disconnect/reconnect power to tie in pv/ess components. we are not upgrading the size of the service not upgrading the meter size”.
Compiled from City of Austin records · updated Sep 20, 2024
- Projects
- 2
- 2 filings
- Latest filing
- Sep 20, 2024
- since Sep 20, 2024
- Largest scope
- —
- Listed value
- —
Where this project stands
FinaledDisconnect/reconnect power to tie in pv/ess components. we are not upgrading the size of the service not upgrading the meter size
- AppliedSep 13, 2024
- IssuedSep 20, 2024
- WorkSep '24 – Oct '24
- Final inspectionOct 18, 2024
Passed final inspection Oct 18, 2024.
1 contact on this project · 1 phone number
Permit & project history
2 projectsDisconnect/reconnect power to tie in pv/ess components. we are not upgrading the size of the service not upgrading the meter size
Disconnect/reconnect power to tie in pv/ess components. we are not upgrading the size of the service not upgrading the meter size
City of Austin permitElectrical PermitFinal- Record
- 2024-124769 EP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Install new 7.82kw rooftop solar system and 13.5kw energy storage system for existing residential only. this is in addition to an existing solar system
Install new 7.82kw rooftop solar system and 13.5kw energy storage system for existing residential only. this is in addition to an existing solar system
City of Austin permitElectrical PermitFinal- Record
- 2024-124762 EP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 7909 Izetta Ln
What is being built at 7909 Izetta Ln?
The latest filing (City of Austin permit 2024-124769 EP, September 20, 2024) covers disconnect/reconnect power to tie in pv/ess components. we are not upgrading the size of the service not upgrading the meter size.
How many permits and filings does 7909 Izetta Ln have?
2 filings across 2 projects, from September 20, 2024 to September 20, 2024.
What is being built near Balcones Re Addison 2022 in Austin?
7909 Izetta Ln is about 443 m from Balcones Re Addison 2022 (8404 Annalise Drive). Its latest filing is for disconnect/reconnect power to tie in pv/ess components. we are not upgrading the size of the service not upgrading the meter size.
Is there other construction near 7909 Izetta Ln?
Yes. Nearby filings include 5317 Bonneville Bnd (request to disconnect. upgrade meter socket, Apr 4, 2024); 8012 Annalise Dr (install tankless replace prv and install halo, Oct 17, 2024); 5405 Daimler Dr (kinsey will tunnel under home following main sewer line in yard at cleanout under garage approx 10ft of tunnel. we will remove broken pvc pipe under garage and install new sched 40 pvc in its place. bed outside trench approx 5 ft in sand and hang pipe from slab every 6 ft. engineer report will be sent to city once tunnel is finished being exposed, Feb 11, 2026).
How do I get alerts for new permits at 7909 Izetta Ln?
Watch this address on groundranger and you'll get an email when a new permit or project filing appears here or nearby.
Also being built nearby
All of 78744- 5317 Bonneville BndApr 4, 2024Request to disconnect. upgrade meter socket · 78 m away
- 8012 Annalise DrOct 17, 2024Install tankless replace prv and install halo · 98 m away
- 5405 Daimler DrFeb 11, 2026Kinsey will tunnel under home following main sewer line in yard at cleanout under garage approx 10ft of tunnel. we will remove broken pvc pipe under garage and install new sched 40 pvc in its place. bed outside trench approx 5 ft in sand and hang pipe from slab every 6 ft. engineer report will be sent to city once tunnel is finished being exposed · 102 m away
- 5305 Bonneville BndAug 16, 2024Install an embr two pole 60 amp breaker and run approximately 140 foot of surface mount of conduit with miscellaneous 90s lbs benz and bell boxes as needed around the entire back of the home to the garage location punch in the wall with an lb and install a customer provided tesla wall connector · 124 m away
- 5216 Bonneville BndMar 4, 2024***emergency*** replace main breaker (200 amp) · 218 m away
- 5201 Bonneville BndJun 11, 2026Etj - 200amp panel replacement *has ae- disconnect and reconnect only · 225 m away
- 5017 Ingersoll LnApr 11, 2024***new solar panels on new solar system*** installation of solar panels on existing residential roof. 5.2 kw · 233 m away
- 5608 Bonneville BndSep 11, 2024Replacement of an existing water heater · 233 m away
- 5124 Bonneville BndJan 3, 2025Disconnect/reconnect to tie in installation of an 882kw pv system · 282 m away
- 5012 Bonneville BndAug 5, 2026Replacement of an existing water heater 50 gallon nat gas water heater replacement · 336 m away
- 8201 Annalise DrOct 5, 2026Install new 200a panel and make the existing main panel a sub panel. no increase to amperage or load. approved espa attached. will need disconnect/reconnect. etj · 348 m away
- 5000 Bonneville BndSep 4, 2026Base: installing a backup battery system and additional meter socket · 365 m away
More warehouses & industrial in 78744, solar installs in 78744.