2300 Standish Dr
Austin, TX 78745
2300 Standish Dr: 1 project on record
City of Austin lists 1 filing across 1 project at 2300 Standish Dr, Austin, TX 78745. The most recent, filed December 10, 2024, covers: “Replacement of complete existing central heat and air system with or without duct work 1 system 4 ton straight cool gas furnace”.
Compiled from City of Austin records · updated Dec 10, 2024
- Projects
- 1
- 1 filings
- Latest filing
- Dec 10, 2024
- since Dec 10, 2024
- Largest scope
- —
- Listed value
- —
Where this project stands
FinaledReplacement of complete existing central heat and air system with or without duct work 1 system 4 ton straight cool gas furnace
- AppliedDec 3, 2024
- IssuedDec 10, 2024
- WorkDec '24 – Dec '24
- Final inspectionDec 23, 2024
Passed final inspection Dec 23, 2024.
1 contact on this project · 1 phone number
Permit & project history
1 projectReplacement of complete existing central heat and air system with or without duct work 1 system 4 ton straight cool gas furnace
Replacement of complete existing central heat and air system with or without duct work 1 system 4 ton straight cool gas furnace
City of Austin permitMechanical PermitFinal- Record
- 2024-158209 MP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 2300 Standish Dr
What is being built at 2300 Standish Dr?
The latest filing (City of Austin permit 2024-158209 MP, December 10, 2024) covers replacement of complete existing central heat and air system with or without duct work 1 system 4 ton straight cool gas furnace.
How many permits and filings does 2300 Standish Dr have?
1 filing across 1 project, from December 10, 2024 to December 10, 2024.
Is there other construction near 2300 Standish Dr?
Yes. Nearby filings include 2302 Standish Dr (replacement of an existing water heater, Oct 29, 2025); 2304 Standish Dr (install additional 2.64 kw dc rooftop solar system and an additional 10.0 kwh energy storage system to existing residential, Jul 29, 2026); 2307 Whitestone Dr (tunnel under slab foundation and replace call cast iron with new pvc 2 access points one through floor in garage and one near exterior front door. 50 total feet of tunnel under slab and new sewer yard line from house tro city sewer tap. *emergency, May 2, 2024).
How do I get alerts for new permits at 2300 Standish Dr?
Watch this address on groundranger and you'll get an email when a new permit or project filing appears here or nearby.
Also being built nearby
All of 78745- 2302 Standish DrOct 29, 2025Replacement of an existing water heater · 17 m away
- 2304 Standish DrJul 29, 2026Install additional 2.64 kw dc rooftop solar system and an additional 10.0 kwh energy storage system to existing residential · 41 m away
- 2307 Whitestone DrMay 2, 2024Tunnel under slab foundation and replace call cast iron with new pvc 2 access points one through floor in garage and one near exterior front door. 50 total feet of tunnel under slab and new sewer yard line from house tro city sewer tap. *emergency · 46 m away
- 2403 Gateshead CirAug 25, 2025Replacement of complete existing central heat and air system with or without duct work · 60 m away
- 2302 Whitestone DrJul 9, 2026Tunnel under foundation to replace cast iron drain lines for 2 full bathrooms kitchen and washer drain lines. 2 access holes will be made one in the front side by doorway entrance and the second by the garage to tunnel and reroute kitchen and second bathroom total length of tunnel is approximately 60 feet of tunnel. sewer line will be replaced from the home to the city tap connection total length of sewer line is approximately 70 feet · 62 m away
- 2306 Standish DrMay 1, 2026Addition and remodel: interior to be completely gutted. some walls to be removed or relocated. all windows and doors to be replaced. minor electrical and plumbing work. replacing roof. exterior work involves a small added patio under front entry area and a small deck in the backyard entry area. front fence relocation. revision 01 to add mp · 63 m away
- 2300 Whitestone DrDec 1, 2025Ev charger installation · 87 m away
- 2303 Whitestone DrJun 4, 2025Replace main panel · 93 m away
- 2307 Berry Hill CirDec 17, 2024Upgrading existing service to 200amps · 107 m away
- 2301 Whitestone DrJan 5, 2026Replacing building sewer line. tunneling up to 70 feet · 112 m away
- 2300 Brookhill DrJun 26, 2025Installing a 125amp main breaker panel and meter can (underground) · 119 m away
- 2306 Brookhill DrApr 11, 2025Dig though ground under foundation to tunnel out and replace up to 50 feet of sewer line. this is for the kitchen and laundry lines only · 131 m away