Two-family duplex permitted at 5511 Joe Sayers Ave

Austin’s building permit filed September 25, 2023, describes new construction of a two-family residential duplex at 5511 Joe Sayers Ave. The plans call for two three-bedroom units, with an attached one-car garage for Unit A and a one-car carport for Unit B; later permits cover a driveway approach and irrigation work.

Summarized from City of Austin records · updated Nov 4, 2025

Projects
4
4 filings
Latest filing
Nov 4, 2025
since Nov 27, 2023
Largest scope
—
Listed value
—

Where this project stands

Finaled

Tceq-compliant components: * 1 dca backflow preventer (in-ground): required by tceq to protect the public water supply from contamination. this device will be tested and registered with the city upon completion. * 1 isolation valve: also required by tceq this allows for emergency shutoff of the irrigation system without affecting the homes water supply. * two 1 master valves (one per controller): as per tceq code a master valve is required for each controller to help prevent line leaks or water loss when the system is off. irrigation zones: * four irrigreen rotor zones: these precision digital rotors map watering patterns for each turf zone reducing overspray and maximizing efficiency. * two drip irrigation zones: installed for landscape beds these zones use subsurface drip tubing with 12 emitter spacing to deliver water directly to plant roots. installation details: * trenching: all piping will be installed at 810 inches deep using trenchers or hand tools depending on site conditions. * controllers and wiring: system will include complete controller installation wiring and testing

  1. AppliedMar 7, 2022
  2. IssuedNov 4, 2025
  3. WorkNov '25 – May '26
  4. Final inspectionMay 8, 2026

Passed final inspection May 8, 2026.

Permit & project history

4 projects
  1. Tceq-compliant components: * 1 dca backflow preventer (in-ground): required by tceq to protect the public water supply from contamination. this device will be tested and registered with the city upon completion. * 1 isolation valve: also required by tceq this allows for emergency shutoff of the irrigation system without affecting the homes water supply. * two 1 master valves (one per controller): as per tceq code a master valve is required for each controller to help prevent line leaks or water loss when the system is off. irrigation zones: * four irrigreen rotor zones: these precision digital rotors map watering patterns for each turf zone reducing overspray and maximizing efficiency. * two drip irrigation zones: installed for landscape beds these zones use subsurface drip tubing with 12 emitter spacing to deliver water directly to plant roots. installation details: * trenching: all piping will be installed at 810 inches deep using trenchers or hand tools depending on site conditions. * controllers and wiring: system will include complete controller installation wiring and testing

    Tceq-compliant components: * 1 dca backflow preventer (in-ground): required by tceq to protect the public water supply from contamination. this device will be tested and registered with the city upon completion. * 1 isolation valve: also required by tceq this allows for emergency shutoff of the irrigation system without affecting the homes water supply. * two 1 master valves (one per controller): as per tceq code a master valve is required for each controller to help prevent line leaks or water loss when the system is off. irrigation zones: * four irrigreen rotor zones: these precision digital rotors map watering patterns for each turf zone reducing overspray and maximizing efficiency. * two drip irrigation zones: installed for landscape beds these zones use subsurface drip tubing with 12 emitter spacing to deliver water directly to plant roots. installation details: * trenching: all piping will be installed at 810 inches deep using trenchers or hand tools depending on site conditions. * controllers and wiring: system will include complete controller installation wiring and testing

    City of Austin permitPlumbing PermitFinal
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  2. Construct new driveway approach of 12 ft. no sidewalk inspection per plan review

    Construct new driveway approach of 12 ft. no sidewalk inspection per plan review

    City of Austin permitDriveway / SidewalksFinal
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  3. New construction two-family residential duplex 3 bedroom (both units) 3 bathroom (unit a) 3.5 bath (unit b) with attached 1-car garage (unit a) attached 1-car carport (unit b) covered front porch (both units) covered rear porch (unit b) and exterior storage (both units)

    New construction two-family residential duplex 3 bedroom (both units) 3 bathroom (unit a) 3.5 bath (unit b) with attached 1-car garage (unit a) attached 1-car carport (unit b) covered front porch (both units) covered rear porch (unit b) and exterior storage (both units)

    City of Austin permitMechanical PermitFinal
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  4. New construction two-family residential duplex 3 bedroom (both units) 3 bathroom (unit a) 3.5 bath (unit b) with attached 1-car garage (unit a) attached 1-car carport (unit b) covered front porch (both units) covered rear porch (unit b) and exterior storage (both units)

    New construction two-family residential duplex 3 bedroom (both units) 3 bathroom (unit a) 3.5 bath (unit b) with attached 1-car garage (unit a) attached 1-car carport (unit b) covered front porch (both units) covered rear porch (unit b) and exterior storage (both units)

    City of Austin permitBuilding PermitFinal
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro

Sources: City of Austin

Questions about 5511 Joe Sayers Ave

What is being built at 5511 Joe Sayers Ave?

The City of Austin building permit describes a new two-family residential duplex. The plans include two three-bedroom units.

When was the duplex at 5511 Joe Sayers Ave permitted?

The building permit, 2022-085445 BP, was filed September 25, 2023. A mechanical permit for the duplex was filed November 27, 2023.

How many units are planned at 5511 Joe Sayers Ave?

The permit describes a two-family duplex with two units. Both units are listed as having three bedrooms.

What features are included in the duplex at 5511 Joe Sayers Ave?

The permit lists an attached one-car garage for Unit A and an attached one-car carport for Unit B. Both units have covered front porches; Unit B also has a covered rear porch, and both include exterior storage.

Was a driveway permitted at 5511 Joe Sayers Ave?

A permit filed October 6, 2025, describes construction of a 12-foot driveway approach. The record is marked final.

What does the 2025 irrigation permit at 5511 Joe Sayers Ave cover?

Permit 2025-141415 PP, filed November 4, 2025, describes irrigation components and zones for turf and landscape beds. The permit record is marked final.

Also being built nearby