Electrical service upgrades filed at 1105 Levee St
Electrical permits at 1105 Levee St indicate upgrades to the building’s power service, including a new 400-amp, 480-volt service and distribution equipment. The first of three City of Dallas permits was filed October 10, 2025; the latest was filed August 14, 2026.
Summarized from City of Dallas records · updated Aug 14, 2026
- Projects
- 4
- 4 filings
- Latest filing
- Aug 14, 2026
- since Oct 10, 2025
- Largest scope
- —
- Listed value
- —
Permit & project history
4 projectsPrimetime electrical contractors will install a new 400-amp electrical service (480volt) for the building to meet current and future power demands. scope includes: • installation of a 400-amp meter base on the exterior of the building in compliance with local utility and nec requirements. • installation of a 400-amp service disconnect adjacent to the meter base to provide a code-compliant means of disconnect. • installation of a 400-amp i-line distribution panel inside the building to serve as the main distribution point for interior loads. • installation of a step-down transformer to reduce the incoming 480v service to 240/120v for existing lighting and receptacle circuits. • wreck out existing interior meter, after the power company cut it off. • all conduit, conductors, grounding, bonding, and terminations will be completed per the code and local authority requirements. • the system will be tested, labeled, and verified for full functionality upon completion
Primetime electrical contractors will install a new 400-amp electrical service (480volt) for the building to meet current and future power demands. scope includes: • installation of a 400-amp meter base on the exterior of the building in compliance with local utility and nec requirements. • installation of a 400-amp service disconnect adjacent to the meter base to provide a code-compliant means of disconnect. • installation of a 400-amp i-line distribution panel inside the building to serve as the main distribution point for interior loads. • installation of a step-down transformer to reduce the incoming 480v service to 240/120v for existing lighting and receptacle circuits. • wreck out existing interior meter, after the power company cut it off. • all conduit, conductors, grounding, bonding, and terminations will be completed per the code and local authority requirements. • the system will be tested, labeled, and verified for full functionality upon completion
City of Dallas permitCommercial Electrical PermitPrimetime electrical contractors will install a new 400-amp electrical service (480volt) for the building to meetcurrent and future power demands.scope includes:• installation of a 400-amp meter base on the exterior of the building in compliance with local utility andnec requirements.• installation of a 400-amp service disconnect adjacent to the meter base to provide a code-compliantmeans of disconnect.• installation of a 400-amp island distribution panel inside the building to serve as the main distributionpoint for interior loads.• installation of a step-down transformer to reduce the incoming 480v service to 240/120v for existinglighting and receptacle circuits.• relocation of the existing interior meter to the exterior location to ensure accessibility and compliancewith utility company regulations.• all conduit, conductors, grounding, bonding, and terminations will be completed per the 2020 neccode and local authority requirements.• the system will be tested, labeled, and verified for full functionality upon completion
Primetime electrical contractors will install a new 400-amp electrical service (480volt) for the building to meetcurrent and future power demands.scope includes:• installation of a 400-amp meter base on the exterior of the building in compliance with local utility andnec requirements.• installation of a 400-amp service disconnect adjacent to the meter base to provide a code-compliantmeans of disconnect.• installation of a 400-amp island distribution panel inside the building to serve as the main distributionpoint for interior loads.• installation of a step-down transformer to reduce the incoming 480v service to 240/120v for existinglighting and receptacle circuits.• relocation of the existing interior meter to the exterior location to ensure accessibility and compliancewith utility company regulations.• all conduit, conductors, grounding, bonding, and terminations will be completed per the 2020 neccode and local authority requirements.• the system will be tested, labeled, and verified for full functionality upon completion
City of Dallas permitCommercial Electrical PermitWe are relocating the meter, set a 400amp disconnect outside fused , for oncor. inside tapped off a gutter to feed 2- transformers and installed 5 indoor disconnects for existing sevice panels and protect the transformers and providing disconnecting means and feeder protection. existing service panels are 1-150 amp main bkr panel and an existing 200 amp panel. just refeeding the existing panels from the new service location., ran 1- 3 phase circuit for a piece of equipment
We are relocating the meter, set a 400amp disconnect outside fused , for oncor. inside tapped off a gutter to feed 2- transformers and installed 5 indoor disconnects for existing sevice panels and protect the transformers and providing disconnecting means and feeder protection. existing service panels are 1-150 amp main bkr panel and an existing 200 amp panel. just refeeding the existing panels from the new service location., ran 1- 3 phase circuit for a piece of equipment
City of Dallas permitCommercial Electrical Permit
Sources: City of Dallas
Questions about 1105 Levee St
What is being built at 1105 Levee St?
City of Dallas permits indicate electrical service and distribution upgrades to the building, including a new 400-amp, 480-volt service and a step-down transformer.
When were permits filed for work at 1105 Levee St?
The three City of Dallas electrical permits were filed October 10, 2025, October 23, 2025, and August 14, 2026.
What does permit COM-ELC-26-003818 cover?
Filed August 14, 2026, the permit covers a new 400-amp, 480-volt electrical service, an interior distribution panel, and a transformer to supply existing lighting and receptacle circuits.
Is a new building planned at 1105 Levee St?
The records provided list electrical permits for the existing building, not a permit for new construction.
What electrical work was permitted at 1105 Levee St in October 2025?
Two City of Dallas electrical permits were filed that month. They describe relocating or replacing service equipment and providing power and protection for existing panels and equipment.
What is happening near Thermo 480v Power on Levee Street?
At 1105 Levee St, City of Dallas permits indicate upgrades to the building’s electrical service and distribution equipment. The latest permit was filed August 14, 2026.
Also being built nearby
All of 75207- 1105 E Levee St · Trips Levee Gp LLCMay 21, 2026Thermo 480v power — renovation/alteration — install 3 phase 480 electrical to building, and change rear exit to swinging door
- 1211 E Levee St · Giamrone Design District Projects LLCMay 20, 2024Sounders event space — renovation/alteration — tenant finish-out
- 1841 Levee StSep 10, 2026Remodel plumbing · 9 m away
- 1839 Levee StOct 29, 2020Gas test · 18 m away
- 1835 Levee StOct 29, 2020Gas test · 36 m away
- 120 Turtle Creek BlvdOct 23, 2026Relocate gas main line · 77 m away
- 1821 Levee StJan 12, 2021To complete work permit 1701111072 · 98 m away
- 1815 Levee StNov 4, 2025Gas test · 125 m away
- 139 Turtle Creek Blvd · N13group, LLCApr 22, 2026Remodel plumbing, tankless water heater. adding three bf devices · 135 m away
- 110 Express StDec 4, 2025Replacing old burned federal pacific 300 amp panel with a new 300 amp electrical panel · 159 m away
- 120 Express StDec 8, 2020Service release no work · 172 m away
- 150 Turtle Creek Blvd · C/O Asana Partners LP ColumbiaJul 16, 2025Dawson agency — renovation/alteration — cabinetry, paint, carpet, tile, dividing walls · 172 m away