A 600-foot section of Bachman Lake Trail at 3842 W Northwest Highway is listed for reconstruction with a wider concrete path. The project was registered with TDLR on July 29, 2025, and is marked closed. Its applicant-estimated cost was $70,000.
Summarized from Texas Department of Licensing and Regulation records · updated Jul 29, 2025
- Projects
- 1
- 1 filings
- Latest filing
- Jul 29, 2025
- since Jul 29, 2025
- Largest scope
- 6,000 sf
- Estimated cost
- $70K
- state registration
Where this project stands
CompletedBachman Lake Trail Improvement
6,000 sq ft · $70K est.
- RegisteredJul 29, 2025
- Plan review
- ConstructionAug '25 – Sep '25
- Inspected
- Closed
Ran as a 1-month build.
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectDemolish approximately 600 linear feet of existing 8-foot-wide asphalt trail and reconstruct it with a new 10-foot-wide, 5-inch-thick reinforced concrete trail in accordance with current city of dallas and ada standards. — bachman lake trail
TDLR project registrationRenovation/AlterationProject Closed6,000 sq ft$70K est.- Project #
- TABS2025024629
- Tenant / owner
- Bachman Lake Trail Improvement
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 3842 W Northwest Highway
What is being built at 3842 W Northwest Highway?
The Bachman Lake Trail Improvement project replaces about 600 feet of existing asphalt trail with a 10-foot-wide reinforced concrete trail. The TDLR registration, filed July 29, 2025, lists the project as closed.
Is a new building going up at 3842 W Northwest Highway?
The listed project is trail reconstruction, not a new building. It covers about 600 linear feet of Bachman Lake Trail.
What will the new Bachman Lake Trail section be made of?
The project description specifies a 10-foot-wide, 5-inch-thick reinforced concrete trail, replacing an existing 8-foot-wide asphalt section.
How much will the Bachman Lake Trail improvement cost?
The TDLR registration lists an applicant-estimated project cost of $70,000. The project is marked closed.
What's happening on W Northwest Highway near Chick-fil-A?
A Bachman Lake Trail project at 3842 W Northwest Highway is registered to replace about 600 feet of asphalt trail with reinforced concrete. The project was registered July 29, 2025, and is listed as closed.
Is the Bachman Lake Trail work near Elan At Bluffview?
The project address, 3842 W Northwest Highway, is listed about 20 meters from Elan At Bluffview. The registered work is reconstruction of a 600-foot trail section.
Also being built nearby
All of 75220- 3842 W Northwest HwyFeb 18, 2025Install in-ground swimming pool
- 3850 W Northwest Hwy · Elan At BluffviewNov 5, 2026# 1202 changeout existing system & install 1.5 ton split system · 20 m away
- 3830 W Northwest HwyNov 17, 2020Service release no work · 30 m away
- 3860 W. Northwest Highway · Pref Bluffview Towers LPSep 16, 2024Root canal dentists — renovation/alteration — tenant improvement · 45 m away
- 3860 W Northwest Hwy · Bluffview Tower WestJan 27, 20254th floor speculative suites — renovation/alteration — tenant improvements · 45 m away
- 3820 W Northwest Hwy · Chick-Fil-A, Inc.Jul 24, 2026Taking out single order window and installing a double sliding door in its place as well as a air curtain and mini split to serve the drive thru area for this added door · 55 m away
- 3833 Lenel DrNov 10, 2025Gas test · 93 m away
- 3880 W Northwest HwyNov 23, 2020Building (bu) commercial renovation · 96 m away
- 3811 Lenel DrNov 16, 2026Contractor shall furnish all necessary labor, materials, tools, and equipment to replace approximately 65 linear feet of existing gas piping throughout the property.the work shall include the following:1. remove and replace approximately 65 feet of existing gas piping using a combination of new black iron steel piping and approved csst (corrugated stainless steel tubing), as required for the installation.2. install new black iron steel gas piping in designated areas underneath the home and along the exterior wall of the residence.3. install new approved csst piping in designated areas, including all required fittings, supports, and connections in accordance with applicable local gas codes and manufacturer specifications.4. remove sections of sheetrock as necessary to gain access to existing gas piping and complete the installation.5. furnish and install three (3) new gas shut-off valves and three (3) new gas flex connectors for the designated gas appliances or connections.6. properly secure, support, and connect all newly installed gas piping.7. perform the required gas pressure test and leak inspection to verify the integrity of the newly installed gas piping system.8. obtain the required plumbing/mechanical permit, as applicable, and coordinate the required inspection with the local authority having jurisdiction.9. restore gas service upon successful completion of the required testing and approval, where applicable · 108 m away
- 3857 Lenel DrSep 19, 2026Install 8' fence · 113 m away
- 3890 W Northwest Hwy · Pref Bluffview Towers, LPOct 12, 2026Emergency repair to entire building 2 pulled and replaced damaged wire from switchgear room in basement of building to oncor transformer outside of building. the entire building is on a temporary transformer · 121 m away
- 3780 W Northwest Hwy · Carroll Concerns Ltd PsJan 29, 2025Midway hollow pet clinic — renovation/alteration — interior renovation of the first floor of an existing veterinary hospital - to include a new interior layout with new interior finishes · 186 m away
More demolitions in 75220.