8161 Moberly Ln
Dallas, TX 75227
Electrical panel replacement at 8161 Moberly Ln
Commercial electrical permits filed in October 2025 indicate replacement of the building’s 4,000-amp main distribution panel with a 2,000-amp panel and installation of a 1,200-amp disconnect. The City of Dallas records list permits COM-ELC-25-002565, filed October 6, and COM-ELC-25-002611, filed October 23.
Summarized from City of Dallas records · updated Oct 23, 2025
- Projects
- 3
- 3 filings
- Latest filing
- Oct 23, 2025
- since Dec 9, 2020
- Largest scope
- —
- Listed value
- $696
- partial · often understated
Permit & project history
3 projectsReplace old/outdated 4000a main distribution panel (mdp-1) which feed the whole building with a new 2000a main distribution panel, install a 1200a service rated fusible disconnect on the right side of the transition box (wire from transformer connected to copper buss which feed the mdp-1 inside. disconnect 4 parallel sets of 1000 kcmil from the transition box and install to the top of the 1200a disconnect and run 4 parallel sets of 400 kcmil from the load side of the 1200a disconnect to the copper buss in the transition box to feed the new 2000a mdp -1. we will need the power disconnected from the transformer in different weekends. first weekend will install 1200a disconnect and temporary run power from the load side of the disconnect to power up existing mdp-2, circuits from mdp-1 will temporarily be relocated to mdp-2 which will feed the building temporary while during the week the old mdp-1 will be removed and the new mdp-1 be installed. the second shut down of the transformer will permanently connect the load side of the 1200a disconnect to the new mdp-1 and circuits will be transferred back to the new mdp-1“
Replace old/outdated 4000a main distribution panel (mdp-1) which feed the whole building with a new 2000a main distribution panel, install a 1200a service rated fusible disconnect on the right side of the transition box (wire from transformer connected to copper buss which feed the mdp-1 inside. disconnect 4 parallel sets of 1000 kcmil from the transition box and install to the top of the 1200a disconnect and run 4 parallel sets of 400 kcmil from the load side of the 1200a disconnect to the copper buss in the transition box to feed the new 2000a mdp -1. we will need the power disconnected from the transformer in different weekends. first weekend will install 1200a disconnect and temporary run power from the load side of the disconnect to power up existing mdp-2, circuits from mdp-1 will temporarily be relocated to mdp-2 which will feed the building temporary while during the week the old mdp-1 will be removed and the new mdp-1 be installed. the second shut down of the transformer will permanently connect the load side of the 1200a disconnect to the new mdp-1 and circuits will be transferred back to the new mdp-1“
City of Dallas permitCommercial Electrical PermitReplace old/outdated 4000a main distribution panel with a new 2000a main distribution panel, install a 1200a service rated fusible disconnect on the right side of the transition box (copper wire to copper buss). disconnect 4 parallel sets of 1000 mcm from copper buss and insert to top of 1200a disconnect and run 4 parallel sets of 400 mcm from the load side of the disconnect to the copper buss
Replace old/outdated 4000a main distribution panel with a new 2000a main distribution panel, install a 1200a service rated fusible disconnect on the right side of the transition box (copper wire to copper buss). disconnect 4 parallel sets of 1000 mcm from copper buss and insert to top of 1200a disconnect and run 4 parallel sets of 400 mcm from the load side of the disconnect to the copper buss
City of Dallas permitCommercial Electrical Permit
Sources: City of Dallas
Questions about 8161 Moberly Ln
What work is planned at 8161 Moberly Ln in Dallas?
City of Dallas permits indicate replacement of an outdated main electrical distribution panel and installation of a 1,200-amp disconnect.
When were permits filed for electrical work at 8161 Moberly Ln?
The City of Dallas filed commercial electrical permits COM-ELC-25-002565 on October 6, 2025, and COM-ELC-25-002611 on October 23, 2025.
Is a new building being constructed at 8161 Moberly Ln?
The records provided describe electrical equipment replacement, not construction of a new building.
What size electrical panel is being installed at 8161 Moberly Ln?
The permits describe replacing the existing 4,000-amp main distribution panel with a new 2,000-amp panel.
What is the 1,200-amp disconnect for at 8161 Moberly Ln?
The permit descriptions indicate it will connect the electrical service to the new main distribution panel.
Also being built nearby
All of 75227- 8282 Moberly LnDec 5, 2025Service upgrade 400 amps · 23 m away
- 8258 Moberly LnFeb 5, 2026Clean and show/ no work · 33 m away
- 8224 Moberly LnJan 4, 2021New construction canopy · 46 m away
- 8208 Moberly LnJan 4, 2021Site work · 53 m away
- 8160 Moberly LnJan 15, 2026Electrical service · 72 m away
- 5204 S Buckner BlvdFeb 17, 2026Electrical work for commercial alteration · 98 m away
- 4844 S Buckner BlvdJun 2, 2026Meter release · 101 m away
- 4858 S Buckner BlvdJan 15, 2021Service release no work · 103 m away
- 4864 S Buckner BlvdMay 7, 2026Interior finish-out and tenant improvement for an automotive paint and body supply retail store within an existing commercial space. work includes installation of retail shelving paint storage and mixing area cashier counter office work area epoxy flooring interior painting lighting and electrical upgrades hvac adjustments wall and ceiling improvements plumbing fixtures if required and installation of business signage space will be used for retail sales paint mixing storage and customer service related to automotive refinishing products and supplies · 103 m away
- 8201 Eastpoint DrDec 1, 2025Clean and show · 206 m away
- 8224 Endicott LnSep 17, 2025Service release no work per oncor need permit · 208 m away
- 8181 Eastpoint DrNov 24, 2020Addition of one access controlled door · 236 m away