Drain and sewer line replacement at 3907 Greystone Dr

A plumbing permit filed March 25, 2026, covers tunneling beneath the home’s foundation to replace cast-iron drain lines serving two full bathrooms, a half bathroom, the kitchen and washer. The work also includes replacing about 55 feet of sewer line from the home to the city tap. The permit is listed as final.

Summarized from City of Austin records · updated Mar 25, 2026

Projects
2
2 filings
Latest filing
Mar 25, 2026
since Mar 25, 2026
Largest scope
—
Listed value
—

Where this project stands

Finaled

Tunnel under foundation to replace cast iron for 2 full bathrooms and half bathroom with kitchen and washer drain. will have 3 access holes one where drain line exits the foundation the second where bathroom is located on the the far right side of the home and the third access hole will be made by the garage total length of tunnel is 60 feet. sewer line will be replaced from the home to the city tap connection on the front left corner of the property total length of sewer line is approximately 55 feet

  1. AppliedMar 9, 2026
  2. IssuedMar 25, 2026
  3. WorkMar '26 – Mar '26
  4. Final inspectionMar 31, 2026

Passed final inspection Mar 31, 2026.

1 contact on this project · 1 phone number

Permit & project history

2 projects
  1. Tunnel under foundation to replace cast iron for 2 full bathrooms and half bathroom with kitchen and washer drain. will have 3 access holes one where drain line exits the foundation the second where bathroom is located on the the far right side of the home and the third access hole will be made by the garage total length of tunnel is 60 feet. sewer line will be replaced from the home to the city tap connection on the front left corner of the property total length of sewer line is approximately 55 feet

    Tunnel under foundation to replace cast iron for 2 full bathrooms and half bathroom with kitchen and washer drain. will have 3 access holes one where drain line exits the foundation the second where bathroom is located on the the far right side of the home and the third access hole will be made by the garage total length of tunnel is 60 feet. sewer line will be replaced from the home to the city tap connection on the front left corner of the property total length of sewer line is approximately 55 feet

    City of Austin permitPlumbing PermitFinal
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  2. Abandon the leaking water line & reroute it overhead

    Abandon the leaking water line & reroute it overhead

    City of Austin permitPlumbing PermitFinal
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro

Sources: City of Austin

Questions about 3907 Greystone Dr

What work is permitted at 3907 Greystone Dr?

A City of Austin plumbing permit covers replacing cast-iron drain lines beneath the home’s foundation and replacing the sewer line to the city tap. The permit was filed March 25, 2026.

Is a new building going up at 3907 Greystone Dr?

The permit describes plumbing repairs to an existing home, not construction of a new building.

What does permit 2026-028506 PP cover?

Permit 2026-028506 PP covers a 60-foot tunnel beneath the foundation to replace drain lines, plus about 55 feet of sewer line from the home to the city tap.

Which rooms are included in the drain line work at 3907 Greystone Dr?

The permit lists two full bathrooms, a half bathroom, the kitchen and the washer.

When was the plumbing permit filed for 3907 Greystone Dr?

The City of Austin permit was filed March 25, 2026, and is listed as final.

How long is the sewer line replacement at 3907 Greystone Dr?

The permit describes approximately 55 feet of sewer line replacement, from the home to the city tap connection.