Where this project stands
FinaledInstall evse
- AppliedJul 15, 2024
- IssuedJul 30, 2024
- WorkJul '24 – Jan '25
- Final inspectionJul 30, 2024
Passed final inspection Jul 30, 2024.
1 contact on this project · 1 phone number
Permit & project history
1 projectInstall evse
Install evse
City of Austin permitElectrical PermitFinal- Record
- 2024-087466 EP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 105 W Skyview Rd
What is being built at 105 W Skyview Rd?
The latest filing (City of Austin permit 2024-087466 EP, July 30, 2024) covers install evse.
How many permits and filings does 105 W Skyview Rd have?
1 filing across 1 project, from July 30, 2024 to July 30, 2024.
Is there other construction near 105 W Skyview Rd?
Yes. Nearby filings include 108 W Skyview Rd (interior renovations - add a half bathroom replace all cabinets & countertops replace electrical panel install new hvac system with ducting install new flooring paint interior & exterior including interior drywall repairs relocate washer & dryer connections in laundry room - add a door leading to laundry room & a sliding door leading to backyard replace existing tub & tile - install new plumbing fixtures ***modifying existing electrical service to add disconnect means-hyatt, Oct 23, 2026); 102 W Skyview Rd (replacement of complete existing central heat and air system with or without duct work, Aug 7, 2024); 110 W Skyview Rd (replacement of complete existing central heat and air system with or without duct work hvac changeout - replace current system with new 3 ton single stage goodman system, Apr 8, 2025).
How do I get alerts for new permits at 105 W Skyview Rd?
Watch this address on groundranger and you'll get an email when a new permit or project filing appears here or nearby.
Also being built nearby
All of 78752- 108 W Skyview RdOct 23, 2026Interior renovations - add a half bathroom replace all cabinets & countertops replace electrical panel install new hvac system with ducting install new flooring paint interior & exterior including interior drywall repairs relocate washer & dryer connections in laundry room - add a door leading to laundry room & a sliding door leading to backyard replace existing tub & tile - install new plumbing fixtures ***modifying existing electrical service to add disconnect means-hyatt · 49 m away
- 102 W Skyview RdAug 7, 2024Replacement of complete existing central heat and air system with or without duct work · 54 m away
- 110 W Skyview RdApr 8, 2025Replacement of complete existing central heat and air system with or without duct work hvac changeout - replace current system with new 3 ton single stage goodman system · 58 m away
- 5810 Link AveMar 11, 2026Replacement of mini-split system ducted minisplit no actual ductwork · 59 m away
- 100 W Skyview RdApr 29, 2025Cap off water wastewater permit total demolition of single-story sfr 1118 sq ft circa 1952 ***the building shall not be demolished until after the contractor has fulfilled the neighbor notification requirements outlined in steps 5 & 6 of the demolition webpage · 64 m away
- 300 W Skyview RdJan 27, 2026Remodel existing shed existing wall to remain all others to be demolished · 73 m away
- 5804 Chesterfield AveAug 12, 2025Bathroom replumb leak repair under pier and beam home issue: a leak has been identified in the cast iron sewer stack beneath the pier and beam home specifically at the section of pipe just before it penetrates the subfloor. cause: the existing plumbing configuration as originally installed ties both the toilet and tub into the same leaking stack. due to this setup and the condition of the materials a full replumb of the bathroom drain system is necessary. work to be performed: all existing cast iron piping serving the bathroom will be cut out and completely removed. the entire bathroom drain system will be replumbed using new pvc sewer piping. new pvc lines will be securely strapped to the underside of the subfloor to ensure long-term stability and to prevent shifting or sagging over time · 74 m away
- 5802 Chesterfield AveMay 19, 2026Replacement of an existing water heater tankless water heater swap (like for like) · 83 m away
- 5714 Avenue DNov 25, 2024Express: change windows replace like for like · 107 m away
- 5717 Avenue DFeb 14, 2025Replacement of complete existing central heat and air system with or without duct work · 129 m away
- 5802 Link AveJun 25, 2025Install electric circuit for range · 130 m away
- 5901 Dillard CirSep 25, 2013Reilly pond detention performance modifications project · 138 m away