1109 Hollybluff St
Austin, TX 78753
Plumbing work and septic-to-sewer cutover at 1109 Hollybluff St
Two plumbing permits filed on February 25, 2026, indicate work to replace underfloor waste and vent piping serving two bathrooms, a washer, and the kitchen sink, and to connect the property from septic to city sewer. The piping work includes concrete demolition and replacement; both permits are marked final.
Summarized from City of Austin records · updated Feb 25, 2026
- Projects
- 2
- 2 filings
- Latest filing
- Feb 25, 2026
- since Feb 25, 2026
- Largest scope
- —
- Listed value
- —
Where this project stands
FinaledReplace all underfloor waste and vent piping. for the 2 bathrooms washer and kitchen sink. to accomplish this we will demolition concrete excavate install have inspected backfill/compact and properly pour back the concrete with engineer approval/letter. approximately 60 x 15 of concrete demolition
- AppliedFeb 19, 2026
- IssuedFeb 25, 2026
- WorkFeb '26 – Mar '26
- Final inspectionMar 16, 2026
Passed final inspection Mar 16, 2026.
1 contact on this project · 1 phone number
Permit & project history
2 projectsReplace all underfloor waste and vent piping. for the 2 bathrooms washer and kitchen sink. to accomplish this we will demolition concrete excavate install have inspected backfill/compact and properly pour back the concrete with engineer approval/letter. approximately 60 x 15 of concrete demolition
Replace all underfloor waste and vent piping. for the 2 bathrooms washer and kitchen sink. to accomplish this we will demolition concrete excavate install have inspected backfill/compact and properly pour back the concrete with engineer approval/letter. approximately 60 x 15 of concrete demolition
City of Austin permitPlumbing PermitFinal- Record
- 2026-019743 PP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Septic to city sewer cutover only
Septic to city sewer cutover only
City of Austin permitPlumbing PermitFinal- Record
- 2026-021899 PP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 1109 Hollybluff St
What work is permitted at 1109 Hollybluff St?
Two City of Austin plumbing permits filed February 25, 2026, cover underfloor waste and vent piping replacement and a septic-to-city-sewer cutover.
Is a restaurant being built at 1109 Hollybluff St?
The available permit descriptions document plumbing work at the property, not restaurant construction.
What does the plumbing permit cover at 1109 Hollybluff St?
Permit 2026-019743 PP covers replacing underfloor waste and vent piping for two bathrooms, a washer, and the kitchen sink. The work description also calls for concrete demolition and replacement.
Is 1109 Hollybluff St connecting to city sewer?
Yes. Permit 2026-021899 PP, filed February 25, 2026, is for a septic-to-city-sewer cutover and is marked final.
When were permits filed for 1109 Hollybluff St?
Both City of Austin plumbing permits were filed on February 25, 2026.
Are the 1109 Hollybluff St permits final?
Both permits, 2026-019743 PP and 2026-021899 PP, are listed with final status.
Also being built nearby
All of 78753- 1113 Hollybluff StJul 1, 2024Cutover from septic to city sewer · 29 m away
- 1107 Hollybluff StFeb 22, 2024Sewer cutover · 30 m away
- 1110 Hollybluff StJul 31, 2026Meter and panel change out grounding gas meter installing 2 ground rods and grounding the panel · 64 m away
- 1103 Hollybluff StOct 8, 2026Cutover from septic to city sewer only ref 2026-129755 ww · 81 m away
- 10607 Denell CirMay 6, 2026Excavate 60 tunnel to repair main drain line under house · 100 m away
- 1114 Hollybluff StApr 16, 2025Cutover from septic to city sewer only · 106 m away
- 1101 Hollybluff StOct 29, 2024Repipe the clothes washer drain line thru the garage outside the right side of the house toward the front of the house. there we will run across the yard and connect to the existing sanitary sewer yard line. we will demolition and patch concrete in the garage as needed to run this new line. we will also cut out the kitchen cabinet bottom and back chip concrete enough to stub out a new waste line for the kitchen sink. we will repair the cabinet after inspections. we include the required engineer inspection and report · 108 m away
- 10611 Denell CirMay 8, 2025Gas line repair · 111 m away
- 10501 Walnut Bend DrMay 29, 2024Replacement of complete existing central heat and air system with or without duct work · 118 m away
- 10613 Denell CirOct 23, 2026Perkin electrical services will remove and replace the existing electrical service equipment and upgrade the system to a new 200-amp electrical service · 133 m away
- 1106 E Applegate DrNov 1, 2024Replacement of complete existing central heat and air system with or without duct work · 137 m away
- 10601 Denell CirDec 3, 2024New pool prefabricated with concrete decking - no plumbing permit required · 142 m away