906 E Applegate Dr
Austin, TX 78753
906 E Applegate Dr: 2 projects on record
City of Austin lists 2 filings across 2 projects at 906 E Applegate Dr, Austin, TX 78753. The most recent, filed March 31, 2026, covers: “Replace a 4 cast iron waste and vent riser from the floor thru the roof. approximately 10 ft. total”.
Compiled from City of Austin records · updated Mar 31, 2026
- Projects
- 2
- 2 filings
- Latest filing
- Mar 31, 2026
- since Mar 31, 2026
- Largest scope
- —
- Listed value
- —
Permit & project history
2 projectsReplace a 4 cast iron waste and vent riser from the floor thru the roof. approximately 10 ft. total
Replace a 4 cast iron waste and vent riser from the floor thru the roof. approximately 10 ft. total
City of Austin permitPlumbing PermitFinal- Record
- 2026-035762 PP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Tunnel and replace the underfloor cast iron waste and vent for the 2 restrooms with pvc
Tunnel and replace the underfloor cast iron waste and vent for the 2 restrooms with pvc
City of Austin permitPlumbing PermitFinal- Record
- 2023-121010 PP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 906 E Applegate Dr
What is being built at 906 E Applegate Dr?
The latest filing (City of Austin permit 2026-035762 PP, March 31, 2026) covers replace a 4 cast iron waste and vent riser from the floor thru the roof. approximately 10 ft. total.
How many permits and filings does 906 E Applegate Dr have?
2 filings across 2 projects, from March 31, 2026 to March 31, 2026.
Is there other construction near 906 E Applegate Dr?
Yes. Nearby filings include 904 E Applegate Dr (the 3/4 water line at the kitchen sink will be capped before it goes into the foundation. we will connect to the existing 3/4 hot water line in the attic and run a new 3/4 hot water line to the back to back bathrooms and will be drop new 1/2 hot lines to the back to back sinks master shower and the hall bathroom tub. this will eliminate the hot water system under the foundation, May 7, 2026); 905 Hollybluff St (65ft tunnel to repair drainage lines then a 35ft trench to repair the main sewer line, Sep 9, 2024); 905 E Applegate Dr (replace all existing underfloor sanitary waste and vent cast iron piping under the floor of this single family residence. this will be accomplished by tunneling under the foundation in the rear of the house to get to the rear bathroom tunneling under the foundation on the east side of the house to get to the second bathroom and running each line out to the existing pvc yard line that was installed 5 or 6 years ago. each tunnel will go in about 8 feet. no tunneling in the right of way. for the washer we will open up the sheetrock chip the exterior concrete grade beam slightly without cutting steel to allow for our new piping to go outside and down below grade on a 45 degree angle. we will do the same with the kitchen sink except instead of cutting sheetrock we will cut the inside bottom and back of the sink cabinet and repipe from the vent down and outside. outside we will collect both the washer line and kitchen sink line and run them to the existing yard line. we will cut some of the concrete patio to accomplish this. this book is an attempt to cover the questions asked by ms. bocanegra on my first attempt at this permit, Jul 7, 2024).
How do I get alerts for new permits at 906 E Applegate Dr?
Watch this address on groundranger and you'll get an email when a new permit or project filing appears here or nearby.
Also being built nearby
All of 78753- 904 E Applegate DrMay 7, 2026The 3/4 water line at the kitchen sink will be capped before it goes into the foundation. we will connect to the existing 3/4 hot water line in the attic and run a new 3/4 hot water line to the back to back bathrooms and will be drop new 1/2 hot lines to the back to back sinks master shower and the hall bathroom tub. this will eliminate the hot water system under the foundation · 25 m away
- 905 Hollybluff StSep 9, 202465ft tunnel to repair drainage lines then a 35ft trench to repair the main sewer line · 55 m away
- 905 E Applegate DrJul 7, 2024Replace all existing underfloor sanitary waste and vent cast iron piping under the floor of this single family residence. this will be accomplished by tunneling under the foundation in the rear of the house to get to the rear bathroom tunneling under the foundation on the east side of the house to get to the second bathroom and running each line out to the existing pvc yard line that was installed 5 or 6 years ago. each tunnel will go in about 8 feet. no tunneling in the right of way. for the washer we will open up the sheetrock chip the exterior concrete grade beam slightly without cutting steel to allow for our new piping to go outside and down below grade on a 45 degree angle. we will do the same with the kitchen sink except instead of cutting sheetrock we will cut the inside bottom and back of the sink cabinet and repipe from the vent down and outside. outside we will collect both the washer line and kitchen sink line and run them to the existing yard line. we will cut some of the concrete patio to accomplish this. this book is an attempt to cover the questions asked by ms. bocanegra on my first attempt at this permit · 64 m away
- 909 E Applegate DrMay 14, 2025Replace sewer line under homes foundation. approximately 80 feet · 70 m away
- 903 Hollybluff StNov 19, 2024We will replace the meter can riser and panel. we will add in surge protection and ground rods as well as bond the gas line to bring the service up to code · 75 m away
- 1001 Hollybluff StFeb 28, 2024Replacement of an existing water heater · 92 m away
- 900 E Applegate DrJun 29, 202640 trench from homeowner cleanout to city tap to replace main building sewer line · 93 m away
- 908 Hollybluff StDec 30, 2025Customer had a four tags 1 four water heater gas line leaking removed any rusted fittings and replaced it with new black iron fittings. fireplace was leaking as well that was tagged there was a copper line feeding fireplace trace that back into the furnace closet using a half inch nipple and a half inch cap. i capped off tee that was feeding copper gas line. put the whole house on test at meter using a 1 inch bell reducer to three-quarter put the pressure at 15 psi it held for 20 minutes pulling inspection for job as well to ensure there are no leaks on the system · 97 m away
- 901 E Applegate DrMar 21, 2024Express: replace 12 existing windows · 106 m away
- 906 Salem LnNov 16, 2023Electrical service replacement. customer currently has ae and is upgrading meter · 108 m away
- 908 Salem LnFeb 24, 2026Replacement of complete existing central heat and air system with or without duct work · 114 m away
- 902 Salem LnJul 9, 2026Replacement of complete existing central heat and air system with or without duct work change out of lennox 3.0 ton merit (up-flow) gas 80% · 123 m away