111 Dallas Street
San Antonio, TX 78205 · Baptist Medical Center
Baptist Medical Center chiller and HVAC upgrades
TDLR records describe HVAC renovations at Baptist Medical Center, including an additional chiller and related pumps. The chiller project was registered July 5, 2024 (TABS2024022438); a separate air-handler and rooftop-unit replacement project was registered October 9, 2023 (TABS2024002712).
Summarized from Texas Department of Licensing and Regulation records · updated Jul 5, 2024
- Projects
- 3
- 3 filings
- Latest filing
- Jul 5, 2024
- since Jul 5, 2024
- Largest scope
- 6,933 sf
- Estimated cost
- $4.5M
- state registration
Where this project stands
CompletedChiller
6,933 sq ft · $700K est.
- RegisteredJul 5, 2024
- Plan review
- ConstructionAug '24 – Dec '24
- Inspected
- Closed
Ran as a 5-month build.
4 contacts on this project · 3 phone numbers
Permit & project history
3 projectsTo install an additional 850 ton chiller, ch-2. a new chilled water pump and new condenser water pump will be installed. to accommodate installation of the new chiller, a new aluminum storefront will be installed after chiller is installation. — baptist medical center
TDLR project registrationRenovation/AlterationProject Closed6,933 sq ft$700K est.- Project #
- TABS2024022438
- Tenant / owner
- Pro
- Design firm
- Pro
- Contact
- Pro
Replacement of a basement level ahu serving kitchen, demolition of two seventh floor ahu, replaced with a seventh floor roof ahu serving ors 1-6, 8-11 and ancillary spaces. replacement of 2 6th floor rtu's serving cath labs 2, 3 and ancillary spaces — baptist medical center
TDLR project registrationRenovation/AlterationProject Closed1,706 sq ft$4.5M est.- Project #
- TABS2024002712
- Tenant / owner
- Pro
- Design firm
- Pro
- Contact
- Pro
Aprox 3,125 sq ft pharmacy renovation to comply with usp 795 & 797 within the existing footprint. millwork and finish upgrades as well. new sink & eyewash in ante room, new sink in 795 area and new staff toilet to replace existing (non-compliant) toilet — baptist medical center
TDLR project registrationRenovation/AlterationReview Complete3,125 sq ft$3.5M est.- Project #
- TABS2023016742
- Tenant / owner
- Pharmacy Renovation
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 111 Dallas Street
What is being built at 111 Dallas Street in San Antonio?
TDLR records describe HVAC upgrades at Baptist Medical Center, not a new building. The work includes an additional chiller, pumps, and air-handler and rooftop-unit replacements.
Is Baptist Medical Center getting a new chiller?
A TDLR registration filed July 5, 2024, describes installing an additional 850-ton chiller and new chilled-water and condenser-water pumps. The project is listed as closed under registration TABS2024022438.
What is the TDLR permit number for the chiller project at 111 Dallas Street?
The TDLR project registration number is TABS2024022438. It was filed July 5, 2024, and is listed as closed.
What HVAC work was registered at Baptist Medical Center in 2023?
A registration filed October 9, 2023, covers replacement and renovation of air-handling units and two rooftop units serving hospital areas. The project number is TABS2024002712, and its status is listed as closed.
How much is the Baptist Medical Center HVAC project estimated to cost?
TDLR lists an estimated cost of $4.5 million for the air-handler and rooftop-unit replacement and renovation project, TABS2024002712. This is an estimate, not a confirmed final cost.
What work is happening at Baptist Medical Center near Fox Tech Campus?
TDLR records identify chiller and HVAC renovations at 111 Dallas Street, about 165 meters from Fox Tech Campus. The chiller registration was filed July 5, 2024, as TABS2024022438.
Also being built nearby
All of 78205- 111 Dallas St · Vhs San Antonio Partners LLCDec 19, 2025Bronchoscopy renovation — renovation/alteration — conversion of existing operating room to new bronchoscopy room and existing ante room into new housekeeping. demolition work for new walls, ceilings, lights, plumbing fixtures, casework. new walls, ceilings, lights, mechanical fan & medgas
- 111 Dallas St. San Antonio, TX 78205 · Vhs San Antonio Partners LLCJun 16, 2025Cath lab #2 equipment replacement — renovation/alteration — cath lab equipment replacement with updated finishes, ceiling, doors, millwork, electrical fixtures, flooring and partitions
- 660 N Main · 660 N MainMay 11, 2026Regus & board room — renovation/alteration — interior finish out for office use · 137 m away
- 637 N Main Ave · Fox Tech CampusJul 12, 2024Saisd bond 2020 fox tech campus additions & renovations — renovation/alteration — renovations and additions of numerous buldings including parking · 165 m away
- 730 N Main · Vhs San Antonio Partners, LLCOct 24, 2025Healthlink — renovation/alteration — interior finish out / renovation · 167 m away
- 611 N. Main Avenue · San Antonio Independent School DistrictDec 3, 2025Bond 2020 fox tech campus additions & renovations west parking lot — new construction — this project consists of the demolition of an existing 2,900 square foot building adjacently located to north flores street on the west side of secondary gymnasium and south of the soccer field. the project includes site clearance for the design of a · 196 m away
- 600 Soledad St · City Of San Antonio - EddMar 21, 2024Launch sa — renovation/alteration — interior wall reconfiguration, update interior paint colors, upgraded 2x2 fixtures to led, move light switches and power outlets in a 7000 sq ft space on the 1st floor · 226 m away
- 215 E. Quincy St · Vhs San Antonio Partners LLCSep 1, 2026Suite 610 — renovation/alteration — interior renovation · 267 m away
- 105 Auditorium Circle · At&t Services, Inc.Mar 22, 2024At&t 105 aud. elevator modernization — renovation/alteration — elevator room modifications · 384 m away
- 105 Auditorium Cir · 105 Auditorium CirMay 6, 20269th & 11th floor aon renovation — renovation/alteration — the development of a “white space” for installation of new telecom racks on the 9th floor and addition of hvac and electrical system to serve the room. on the 11th floor, the existing open space will be utilized to house new electrical substation, an · 384 m away
- 445 Main Avenue · Art Pace, Inc.Oct 14, 2024Art pace rooftop solar canopy — additions to existing building — steel framing for rooftop solar canopy (solar by others) and the addition of a bar/service area, restroom facilities, and a storage area · 420 m away
- 300 Convent St Level 21 And 22 · 300 Convent LLCAug 16, 2024Amegy bank san antonio — renovation/alteration — renovation of level 21 and level 22 office tenant suite space · 431 m away