Dallas permits indicate the existing laundry house at 9025 Forest Ln is being remodeled into a restaurant. A demolition permit was filed December 1, 2025, followed by an alteration permit on March 6, 2026, and plumbing and electrical permits on April 7, 2026.
Summarized from City of Dallas records · updated Apr 7, 2026
- Projects
- 4
- 4 filings
- Latest filing
- Apr 7, 2026
- since Dec 1, 2025
- Largest scope
- —
- Listed value
- —
Permit & project history
4 projectsSources: City of Dallas
Questions about 9025 Forest Ln
What is being built at 9025 Forest Ln?
Permits describe remodeling the existing laundry house into a restaurant. The alteration permit is COM-ALT-ADD-25-001648, filed March 6, 2026.
When was the restaurant project at 9025 Forest Ln permitted?
The alteration permit was filed March 6, 2026. Plumbing and electrical permits followed on April 7, 2026.
Was a building at 9025 Forest Ln demolished?
A commercial demolition permit, COM-DEM-25-000107, was filed December 1, 2025. The record describes it as a demolition permit but does not specify what was demolished.
What plumbing work is planned at 9025 Forest Ln?
A commercial plumbing permit filed April 7, 2026, lists one toilet and one lavatory. The permit number is COM-PLM-26-001324.
What electrical work is planned at 9025 Forest Ln?
A commercial electrical permit filed April 7, 2026, lists nine ceiling fans and 10 plugs. The permit number is COM-ELC-26-001528.
When will the restaurant at 9025 Forest Ln open?
The available permit records do not give an opening date.
Also being built nearby
All of 75243- 9035 Forest LnMar 31, 2026Installing (4) 2 pole 20 amp circuits for the freezers and coolers; relocating some circuits. adding a 100 amp subpanel · 15 m away
- 9009 Forest LnJun 23, 2025Adding an emergency backup generator. chaing entire electrical service and adding 2 transfer switches · 24 m away
- 8989 Forest LnSep 15, 2026Mcr just paint, front drywall & add two doors · 53 m away
- 11835 Greenville AveDec 3, 2025Building 1: remove the existing tpo membrane as needed to replace insulation. replace approximately 2,690 sq ft of wetted insulation found during the moisture survey with an average thickness of 4 inches, and install new poly iso as needed to fill.install a 0.5 inch eps fanfold cover board over the entire roof surface, which ensures a protective surface for the new membrane while adding additional insulation.install new flashings on all penetrations.install new 24-gauge drip edge along eaves. detach and reset the existing parapet coping metal with the new termination bar.adhere the new tpo to the front parapet wall.install new 60-mil tpo membrane mechanically attached per manufacturer's specifications.building 2:clean the existing modified bitumen roof system of loose debris.replace approximately 469 sq ft of wetted insulation found during the moisture survey with an average thickness of 2 inches.install a 0.5” eps fanfold cover board over the entire roof surface, which ensures a protective surface for the new membrane while adding additional insulation.install new flashings on all penetrations.install new 24-gauge drip edge along eaves. install tapered insulation 8 feet out from the front parapet wall to promote positive drainage.remove xl abandoned satellite dish and dispose.replace existing parapet coping metal due to poor condition - pre-finished.install new 60-mil tpo membrane mechanically attached per manufacturer's specifications.building 3:clean the existing modified bitumen roof system of loose debris.replace approximately 289 sq ft of wetted insulation found during the moisture survey with an average thickness of 2 inches, and install new poly iso insulation as needed to fillinstall a 0.5” eps fanfold cover board over the entire roof surface, which ensures a protective surface for the new membrane while adding additional insulation.install new flashings on all penetrations.install new 24-gauge drip edge along eaves. replace existing parapet coping metal due to poor condition - pre-finished.install new 60-mil tpo membrane mechanically attached per manufacturer's specifications.this scope does not include removing the roof to the deck - it is an overlay. the deck/substrate will not be removed during the overlay process, we are only removing and replacing specific areas of insulation that are saturated with moisture, as required by the manufacturer · 155 m away
- 9728 Greenville Ave · Bank OzkMay 22, 20257 pneumatic thermostats7 supply air diffusers6 return grilles · 179 m away
- 9131 Forest LnSep 21, 2026Clean and show.location is vacant · 216 m away
- 11911 Greenville AveApr 8, 2026Apt-4120- changeout system- install 2.5 air handler and condenser · 238 m away
- 11880 Greenville AveJul 22, 2026House power meter is requesting to be released for new tenant occupant · 249 m away
- 9006 Windy Crest DrJul 20, 2026Emergency meter repair · 255 m away
- 11886 Greenville AveApr 29, 2026Run gas to bunsen burners · 259 m away
- 9622 Greenville AveJul 17, 2026Installing 50 gallon electric water heater in closet · 273 m away